Oola Hills West, Oola, Co. Limerick
Planning application 2345
DecisionRefused
Decided22 March 2023
Application typePERMISSION
Source documents1
Site
What is on file
0refusal reasons0conditions8nearby records
Proposed development
Application description published by Limerick County Council.Decision details
Core application dates and identifiers from the public planning record.Planning analysis
Refusal reasons and planning conditions extracted from the public decision file.Refusal reasons
Refusal reasons not machine-readable
Documents are indexed. Reason extraction for Limerick has not started yet.
Conditions
No conditions
No conditions are on record for this application yet.
Planning a project near Oola Hills West, Oola, Co. Limerick?
Get a site risk brief with the local decision pattern and up to 80 detailed nearby comparables (40 refusals and 40 grants), including extracted reasons and source links. €29 incl. VAT, PDF by email.Source documents
Original council portal records and source PDFs where available.- Application fileApplication file on eplanning.ieSource portal
Nearby precedent
Similar nearby applications linked to this planning decision.- 2560122The demolition of a small single storey store to the south east of the Public House and its replacement with residential accommodation spread over 2 levels and joining in to the present first floor level over the Public House for use as their private family home, as well as the construction of 2 no. 2 storey houses (2 units in total, semi-detached) on the vacant site to the immediate southeast of the public house, with vehicular access from the minor road to the northeast of the site, as well as all associated site works on and under land including entrance gates, boundary treatment, connections and all ancillary site works / 0.6 km away / 10 April 2025Refused
- 2560047Entrance, dwelling house, sewage treatment system and percolation area / 0.9 km away / 21 March 2025Refused
- 2346The construction of a dwelling house, detached garage, recessed site entrance, wastewater treatment system with all ancillary site works / 2.2 km away / 22 March 2023Refused
- 2461280The construction of a dwelling house, detached garage, recessed site entrance, wastewater treatment system with all ancillary site works / 2.2 km away / 19 February 2025Refused
- 2461308The construction of a new dwelling house with detached domestic garage, wastewater treatment system & percolation area, improvements to existing entrance gateway and all associated site works / 2.3 km away / 25 February 2025Refused
- 211565A 10-year permission and 35 year operation for a solar farm on four land parcels as described herein; North Parcel(Gortnakistin townland) approximately 23.78 hectares, Central Parcel(Ballyvalode & Keeloges townlands) approximately 43.49 hectares, South Central Parcel(Gortyvahane and Moanroe townlands) approximately 34.7 hectares, South Parcel(Garryduff, Moanroe, Moanoola and Kilmacogue townland) approximately 39.27 hectares. The Central Parcel, South Central Parcel and South Parcel are collectively referred to as the Main Solar Farm; a route corridor of 0.58 hectares for an underground internal network cable along the R507 and L5040 public roads for approximately 600 metres and within the solar farm lands for approximately 1,260 metres. The total site area for the proposed development is approximately 141.8 hectares. The proposed development on these parcels comprises of 755,000sqm of solar photovoltaic panels on ground mounted steel frames; inverter/transformer stations; underground power and communication cables and ducts; boundary security fencing; new internal access tracks; associated drainage infrastructure; site entrances to the R507 public road(site entrance to main solar farm) and the L5040 public local road(North Parcel); CCTV cameras and all associated site services and works. Works for the internal network cable comprise trenching for an underground medium voltage electrical cable and associated joint bays and infrastructure, for a distance of approximately 560 metres on the R507 Regional Road, approximately 100 metres on the L5040 Local Road and approximately 1,260m within the solar farm lands. As part of a separate Strategic Infrastructure Development(SID) planning application provision of a 110kV electrical substation with electrical control building, associated compound with palisade fence and 2no. overhead line masts, which is to be located within the main solar farm, will be lodged with An Bord Pleanála in due course. A Natura Impact Statement (NIS) will be submitted to the Planning Authority with the application / 2.3 km away / 14 January 2022Refused
- 20531Construct 8 No. two bedroomed, semi detached bungalows and 1 No. 4 bedroomed detached bungalow and ancillary works / 2.8 km away / 26 April 2021Refused