SD22A/0274: Permission for the proposed green energy initiative development consisting of the installation of Photovoltaic Panels on the existing roof structures together with all associated site works
Unit 4, Westgate Business Park, Ballymount, Dublin 24
DecisionGrant permission
Decided10 August 2022
Application typePermission
Source documents1
Site
What is on file
0refusal reasons0conditions8nearby records
Decision details
Core application dates and identifiers from the public planning record.Planning analysis
Refusal reasons and planning conditions extracted from the public decision file.Refusal reasons
No refusal reason on record
Documents are indexed. Reason extraction for South Dublin has not started yet.
Conditions
No conditions
No conditions are on record for this application yet.
Planning a project near Unit 4, Westgate Business Park, Ballymount, Dublin 24?
Get the precedent report for this site: every grant and refusal within 5 km, and the planners' reasons. €49 incl. VAT, PDF by email.Source documents
Original council portal records and source PDFs where available.Nearby precedent
Similar nearby applications linked to this planning decision.- SD14A/0229Erection of a palisade fence on a concrete plinth (total height 2400mm) along part of the northeast side of the property with 1 sliding gate including an automated opening and closing function; erection of a steel railing fence on a concrete plinth (total height 2400mm) along part of the northeast side of the property with 1 manually operated personnel gate including footpath to connect with the estate footpath; erection of a palisade fence on a concrete plinth (total height 2400mm) along the northwest side of the property; 1200mm high 150 x 150mm steel columns/bollards set inside the fencing; associated works. / 0.0 km away / 18 December 2014Granted
- SD15A/0116Modification of previously approved fencing (Ref No: SD14A/0229) along the northwest side of the property to include the erection of a palisade fence on a concrete plinth ( total height = 2400mm) inside the boundary line, with 1220mm high steel columns/bollards set inside part of the fencing, and with electric fence (total height = 4000mm) & 1220m high steel columns/bollards set inside the remaining part of the fencing. The erection of a palisade fence on a concrete plinth (total height = 2400mm) with electric fence (total height = 4000mm) & 1220mm high steel columns/bollards set inside the fencing, to the left of the northeast elevation of the existing building, and along the southeast, and southwest sides of the property. The section of fencing to the left of the northeast elevation of the existing building will incorporate 1 sliding gate including an automated opening and closing function. The erection of a projecting angled electric fence (total height = 1000mm) fixed to the face of all elevations of the existing building near the parapet along the perimeter of the roof. The erection of 4 steel columns (total height = 5000mm) to the roof of the existing building to supoort steel cables for the prevention of attack by helicopter. The construction of a 153.1sq.m single storey extension at the existing 2 vehicle access doors to southwest/rear of the building to create 2 vehicle security access traps. The parapet height of the extension will match the parapet height (7,890mm approximately) of the existing canopy covering the area outside the current vehicle access points. 3 bollards, that are electro-automated to retract into ground to be installed outside each of the 2 vehicle access traps. 1 new escape door to the northwest elevation. 1 new escape door to the southwest elevation. Associated works. / 0.0 km away / 23 June 2015Granted
- SD19A/0005Construction of 1,540sq.m approx. of additional hardstanding on northeast and southwest areas of the site for parking of cars and service vehicles; associated works. / 0.0 km away / 18 June 2019Granted
- SD20A/0160Erect 1,063.05sq.m of photovoltaic panels on the roof of existing building with all associated site works. / 0.1 km away / 31 August 2020Granted
- SD21A/0214Retention for as constructed extended floor areas to ground floor level reception area (approx. 38sq.m) and first floor level office areas (approx. 49sq.m). Permission to construct a new extension to the north-eastern corner of a permitted storage warehouse building together with associated external signage, site development works; provide additional storage space at second floor level only (approx. 2,198sq.m) and form an undercroft to the permitted access/entrance areas. / 0.1 km away / 26 January 2022Granted
- SD24A/0075WRetention Planning Application to carry out the following developments to a permitted storage warehouse (Planning Reg. No.'s SD22A/0104, SD21A/0214, SD15A/0254), located at M50 Business Park beside the M50 Ballymount Interchange. The development will consist of (1) Retention Permission for as constructed extended floor area to first floor level storage area (approx. 200 sqm). (2) Retention Permission for as constructed additional stair core (Stair 05) and revised location and layout to permitted stair core (Stair 04). (3) Retention Permission for omission of solid masonry / RC wall to undercroft at north-east elevation. (4) Retention Permission for inclusion of a new pedestrian door to existing building, adjacent to main entrance door to reception area. / 0.1 km away / 30 May 2024Granted
- SD22A/0104Construct additional floors at third and fourth floor levels internally as modifications to a recently permitted development under SD21A/0214 - extension of an existing storage warehouse building. / 0.1 km away / 07 June 2022Granted
- SD16A/0456(1) Construct a new extension to the eastern corner of a permitted storage warehouse building, together with associated external signage, staff & customer car parking, and site landscaping. The proposed extension would provide additional storage space at second floor level only (approx. 778sq.m), and ancillary office space at first floor level (approx. 50sq.m) and form an undercroft to the permitted access/entrance areas. (2) Alterations to the permitted storage warehouse building comprising of: (a) remove external dock leveller located on north-west elevation, (b) amendments to the external elevations of the building comprising of a revised use of permitted colour scheme, and revised door and window locations, (c) revisions to internal layout at ground floor level on site beside the M50 Ballymount Interchange and M50 slip road to the south and southwest and Calmount Avenue. / 0.1 km away / 23 February 2017Granted