Executive snapshot
12% of nearby decided applications were refused. The site check found 249 decisions within 5 km, 2 exact-site or onsite candidate records, and 5 structured appeals.
Evidence maturity
Each section reports its own coverage. “Not yet covered” means no conclusion is drawn while source datasets or policy extraction are still being loaded.
2 register records are within the point-match tolerance; a parcel boundary is needed to treat this as exact.
2 matchedCurrent indexed zoning and settlement layers are intersected with the selected site where coverage exists.
Current section-and-page citations have not yet been loaded for this authority.
Each layer reports its own coverage; missing coverage never appears as a clean result.
0 prompts are backed by extracted nearby decision evidence; all prompts remain checks, not predictions.
5 structured nearby appeal records.
5 matchedHistoric extracted references are not presented as current policy; verified citations are still being loaded.
Open preview
Open preview
For continued use of the existing quarry (granted under Planning Ref. File No.: 06/2275 and ABP Ref.: PL07.222783), including drilling, blasting, crushing, processing, and stockpiling of mate-rials within a total site area of 15.09 hectares to the permitted depth of 33m OD. Continued use of existing permitted structures and facilities, including: weighbridge and wheelwash with side and overhead spray bar, office and staff facilities building and carpark provision (Ref. 17512). Asphalt plant (Ref. 15104), concrete batching plant (Ref. 20419), maintenance shed (Ref. 141295), aggregate shed, ESB substation (Ref. 191964), crushing and screening plant, and stock bays (Ref. 062275 & 21442). Associated site infrastructure. Construction of a new quarry storage yard (c. 1.09 Ha.) to the east of the existing quarry. Relocation of the existing permitted sheds (Plan Ref File No. 21442) to an area beside the proposed storage yard area. Importation of soil and stone (both waste and non-waste) for site restoration purposes and selected construction and demolition waste for recycling to preserve natural aggregate re-sources, subject to the necessary authorisations. The proposed development will facilitate the continued operation and restoration of the site, with the operational life of the quarry ceasing upon resource exhaustion, followed by resto-ration to agricultural and natural uses using imported material. The proposed development is within an overall application area of c. 16.3 hectares and is for a total period of 35 years (comprising an operational period of 33 years followed by 2 years for restoration). The application is accompanied by an Environmental Impact Assessment Report (EIAR)
1. Provision of a steel frame and cladding to cover existing aggregate stock bays for environmental purposed.2. the provision of a steel frame and cladding around the existing fixed plant (including lime crusher) for environmental purposed. the proposed development is ancillary to the main quarry which was previously approved under planning reference 06/2275 and An Bord Pleanála reference PL.07.222783.
For development consisting of the installation of a substation building comprising of an ESB supply room and 2 no. switch rooms (c. 70 sq.m) within a planning application area of c.0.007 Ha. Gross floor space of proposed works: 70 sqm
To construct a concrete Batching Plant on and adjacent to a quarry site previously approved under planning reference 06/2275 and An Bord Pleanála reference PL.07.222783. The proposed development is ancillary to the main quarry and it will include the following: washdown/surface water collection system and washwater recovery tanks; aggregate storage bins; concrete block-making and storage facilities and all ancillary site services.
For the construction of a Concrete Batching Plant on and adjacent to a Quarry site previously approved under Planning Reference 06/2275 and An Bord Pleanala Reference PL.07.222783. The proposed development is ancillary to the main Quarry and it will include the following; Washdown/Surface Water Collection System and Washwater Recovery Tanks. Concrete Block Making and Storage Facility and all Associated Ancillary Site Services. The Planning Application is accompanied by a Natura Impact Statement (NIS).
To construct a dwelling house and garage with treatment plant and percolation area. Gross floor space of proposed works: 175.40 sqm (house) & 44 sqm (garage)
The brief summarizes the pattern across all 249 matched decisions within 5 km and includes up to 80 detailed comparables (40 nearest refusals and 40 nearest grants), with extracted reasons, quotes, and available source links. €29 incl. VAT.
Source match
Matched from public planning record 2560750The site brief adds up to 80 nearest detailed grants and refusals, extracted source evidence, document links, and a shareable risk summary.
Included in site brief
Included in site brief
Included in site brief
Included in site brief