Applications tied to the site
Partial coverage12 register records are within the point-match tolerance; a parcel boundary is needed to treat this as exact.
12 matchedSite planning risk brief
One-off house / within 5 km where a location match is available
Executive snapshot
9% of nearby decided applications were refused. The site check found 868 decisions within 5 km, 12 exact-site or onsite candidate records, and 0 structured appeals.
Evidence maturity
Each section reports its own coverage. “Not yet covered” means no conclusion is drawn while source datasets or policy extraction are still being loaded.
12 register records are within the point-match tolerance; a parcel boundary is needed to treat this as exact.
12 matchedCurrent indexed zoning and settlement layers are intersected with the selected site where coverage exists.
Current section-and-page citations have not yet been loaded for this authority.
Each layer reports its own coverage; missing coverage never appears as a clean result.
0 prompts are backed by extracted nearby decision evidence; all prompts remain checks, not predictions.
No structured appeal row is currently tied to the matched decision set.
Historic extracted references are not presented as current policy; verified citations are still being loaded.
Open preview
Open preview
Construction of the following (1) Two no. light industrial / warehouse units (Unit No. 5 and Unit No.6) with ancillary office space (Unit No. 5 is suitable for sub-division into two no. units) (2) ESB sub-station building (3) minor alterations to the commercial park access road and associated spur roads for access to the individual sites to that which was granted under Planning Ref. No. 17/6290 (4) Signage, car parking, site lighting, storm water attenuation systems and roof top solar PV panels and (5) all associated site development and landscape works.
Development at the existing distribution centre (including ancillary internal offices), which consists of retention of (1) increased internal office floor area, (2) alterations to elevations of building to include windows at first floor of south elevation to facilitate increased ancillary internal offices.
Permission for the construction of 1 light industrial unit with ancillary office space, car parking and all associated site development and landscaping works at Unit 6, Lower Courtstown, Little Island, Cork.
Permission for retention of the constructed ESB sub-station in its current location in lieu of the location granted in Planning Register No. 17/4638.
Construction of the following: (1) Two no. warehouse units (Unit No. 7A & Unit No. 7B) with ancillary office space, (2) Minor alterations to the northern end of the commercial park access road which was granted under planning permission reference no. 21/04093, (3) Signage, car parking, site fencing, site lighting, drainage systems and roof top solar PV panels and (4) all associated site development and landscape works
Permission for an extension for a research and development lab with internal office space over two floors. Permission is also sought for elevational changes to include an additional door to the eastern side of the existing warehouse. The extension is located on the northern side of the warehouse.
The brief summarizes the pattern across all 868 matched decisions within 5 km and includes up to 80 detailed comparables (40 nearest refusals and 40 nearest grants), with extracted reasons, quotes, and available source links. €29 incl. VAT.
Source match
Matched from public planning record 21/4093The site brief adds up to 80 nearest detailed grants and refusals, extracted source evidence, document links, and a shareable risk summary.
Included in site brief
Included in site brief
Included in site brief
Included in site brief