Intend to apply for Permission for A Battery Energy Storage System facility to include up to 85 no. containerised battery storage modules on concrete bases, 20 no. transformer and power conditioning units, cable racks, and associated lighting. 2) Associated development including internal access roads, security gates, palisade perimeter security fencing, acoustic barrier, site drainage and all other works required to facilitate the development. AI Rcvd 30/04/2025
Planning precedent report
Search a place or planning reference, choose the development type, then preview the report before generating the full PDF.Planning precedent report
Huntstown Power Station, In the townlands of Hunstown and Johnstown, C
One-off house / within 5 km where a location match is available
Executive snapshot
Local planning pattern
11% of nearby decided applications were refused. The preview found 2,751 nearby planning records within 5 km where a location match is available.
- Matched source
- FW24A/0400E
- Project type
- One-off house
- Coverage
- 5 km radius
Open preview
Top refusal reasons nearby
Open preview
Nearest similar decisions
The replacement of approx. 251 m of existing 2.4 m high chainlink perimeter fencing and associated access / emergency gates with new 2.4 m high security fencing, gates and all associated site works.
The development will consist of a Battery Energy Storage System (BESS)
The development is a wastewater treatment plant comprising a 3m high b
The development will consist of upgrade works and alterations to an existing renewable bioenergy plant as granted permission under planning reference FW13A/0089 (as extended under extension of duration FW13A/0089/E1) and as granted permission for an increase in the volume of waste imported under planning reference FW18A/0159. The proposed works consist of: (i) Provision of a Biomethane Upgrader, comprising a biogas scrubber and a compression unit; (ii) Provision of a Biomethane Nework Entry Facility (BNEF) with associated proane tanks and perimeter fencing; (iii) Amendment to operating hours with removal of condition 5 of permission FW13A/0089 to permit waste being accepted into the facility 24 hours per day and outputs also being removed from the site 24 hours per day to facilitate operations; (iv) Ancillary site development works. Access will be through existing permitted vehicular accesses onto the R135 Regional Road. The application relates to development which comprises or is for the purpose of an activity requiring an industrial emissions licence issued by the Enviromental Protection Agency.
Planning Permission to erect 1,795.23 m2 or 371.68 Kwp of photovoltaic panels on the roof of our existing Huntstown Power Station plant with all associated site works at Huntstown Bioenergy Limited, Johnstown, Dublin, D11 N28R, site that currently operates under an Industrial Emissions (IE) License (P0993-02).
The full report covers all 2,751 decisions within 5km — with the planner's exact reasons, verbatim quotes and policy citations — delivered as a PDF. €49 incl. VAT.
Source match
Matched from public planning record FW24A/0400EThe full report adds the full list of similar grants and refusals, source quotes, document links, and a shareable PDF summary.