Conditional grantDecided 09 July 2020Carlow County Council

20115: The proposed construction of a 4-bay slatted unit and suspended feed passage, to a proposed height of 6.450m, over side by side effluent tanks, as well as the construction of a retaining wall, and construction of an effluent tank in an Existing concrete floor shed, along with all associated ground works.

Aclare, Myshall, Co. Carlow
DecisionConditional grant
Decided09 July 2020
Application typePERMISSION
Source documents3

Site

What is on file

0refusal reasons13conditions8nearby records

Decision details

Core application dates and identifiers from the public planning record.

Planning analysis

Refusal reasons and planning conditions extracted from the public decision file.

Refusal reasons

No refusal reason

No refusal reason is on record for this application yet.

Conditions

  • , Development to be carried out in accordance with plans received 01/04/20.Compliance
  • , Permission authorises only the development detailed in the submitted plans.Compliance
  • , External concrete walls to have a neutral coloured finish; roof and side wall sheeting/panels to be dark green with a matt finish.Design Materials
  • , Site to be used for agricultural purposes only; no commercial purpose other than incidental to farming.Occupancy
  • , All existing mature trees and hedgerows on and bounding the site to be retained and maintained in situ.Environment Ecology
  • , Sight lines at entrance to public road per DMRB; road opening works subject to Road Opening Licence per Guidelines (2007).Traffic Access
  • , Only clean roof/yard water to soak pits per BS8301/BRE 365. Development to comply with S1605/2017 (Good Agricultural Practice) and TAMS specifications. Construction noise/vibration per BS 5228.Wastewater Drainage
  • , Development must not impair existing roadside drainage. No surface water runoff to public road or adjoining properties. All surface water collected/disposed to soakways per BS 8301:1985 and BRE Digest 365.Wastewater Drainage
  • , Connection to Irish Water network requires prior agreement. Compliance with Irish Water CDS Technical Documentation required. Connections subject to Irish Water Capital Investment Programme constraints.Water Services
  • , Adequate off-carriageway parking for construction traffic. No parking on public road. Measures to prevent muck/dirt on road. Site kept neat/litter-free. Noise/dust emissions limited.Construction Management
  • , Construction hours restricted to Mon-Fri 08.00-18.00 and Sat 08.00-13.00. No work on Sundays/Bank Holidays without prior written approval.Construction Management
  • , Service poles to be relocated prior to construction at applicant's expense. All ESB/telecom cables to be located underground unless otherwise agreed.Other

Source documents

Original council portal records and source PDFs where available.

Nearby precedent

Similar nearby applications linked to this planning decision.