Conditional grantDecided 22 March 2024Carlow County Council

2460004: New dwelling, new on site waste water treatment system, new site entrance, new bored well and all associated site works

Aclare, Myshall, Co. Carlow
DecisionConditional grant
Decided22 March 2024
Application typePERMISSION
Source documents6

Site

What is on file

0refusal reasons15conditions8nearby records

Decision details

Core application dates and identifiers from the public planning record.

Planning analysis

Refusal reasons and planning conditions extracted from the public decision file.

Refusal reasons

No refusal reason

No refusal reason is on record for this application yet.

Conditions

  • 1Development must follow approved plans received 09/01/2024 and amended 04/03/2024.Compliance
  • 2Permission only covers the specific development detailed, excluding other exempted development.Compliance
  • 3Dwelling must be first occupied as permanent residence by applicant and immediate family for 7 years. Section 47 agreement required before commencement.Occupancy
  • 4External finishes per approved drawings: neutral plaster and locally sourced stone. No white uPVC for windows, doors, or rainwater goods.Design Materials
  • 5Landscaping per approved Landscape Report. Planting within first season, protect from damage, replace failures within 5 years.Landscaping Boundary
  • 6Sight lines per DMRB and Drawing 004 established before construction. Verge kept clear. Entrance gateway max 1.5m using local materials.Traffic Access
  • 7Surface water collected to soakaways per BRE Digest 365. No discharge to public road or adjoining properties. Road opening works require licence.Wastewater Drainage
  • 8Strict separation: only clean surface water to soakpits; only foul/soiled water to wastewater treatment system.Wastewater Drainage
  • 9On-site system per EPA Code of Practice (June 2021). Certificate of Compliance with as-constructed drawings required before occupation. Grease trap installed. Surface water excluded.Wastewater Drainage
  • 10Connection agreement with Uisce Éireann required before commencement. Comply with Technical Documentation and Capital Investment Programme constraints.Water Services
  • 11Off-carriageway parking for construction traffic. No parking on public road. Keep site clean, control noise/dust, prevent debris on road.Construction Management
  • 12Construction hours restricted to Mon-Fri 08:00-18:00 and Sat 08:00-13:00. No work on Sundays or Bank Holidays.Construction Management