Conditional grantDecided 12 March 2020Carlow County Council

209: The construction of (i) A new treated water storage tank, (ii) New transfer pumps and local control panel within a weather-proof enclosure, (iii) Demolition of contact tanks, (iv) Ancillary development works and (v) Associated temporary development works, including a temporary compound area for the construction period

Royal Oak Road, Bagenalstown Ind. Park, Kilree Td. Bagenalstown
DecisionConditional grant
Decided12 March 2020
Application typePERMISSION
Source documents3

Site

What is on file

0refusal reasons14conditions8nearby records

Decision details

Core application dates and identifiers from the public planning record.

Planning analysis

Refusal reasons and planning conditions extracted from the public decision file.

Refusal reasons

No refusal reason

No refusal reason is on record for this application yet.

Conditions

  • , Development carried out in accordance with plans received 20/01/20.Compliance
  • , Permission limited to development detailed in application; excludes other site development.Compliance
  • , Existing boundary hedging retained and maintained.Landscaping Boundary
  • , Entrance sightlines per Carlow Co. Development Plan 2015-2021 Sec 11.19.1; on-site parking per Sec 11.19.4; no interference with public road/footpath without Engineer agreement; Construction Management Plan submitted prior to commencement.Traffic Access
  • , Do not impair existing roadside drainage; no surface water to public road/adjoining properties; surface water disposed to soakways/system per BS 8301:1985 and BRE Digest 365.Wastewater Drainage
  • , Only clean surface water to soakpits/system; no discharges to rear of site during construction/operational phases.Environment Ecology
  • , Construction Environmental Management Plan strictly implemented.Construction Management
  • , Waste Management Plan submitted prior to commencement, detailing EWC codes, tonnages, reuse, disposal, soil arrangements, hazardous waste, segregation, and permits.Construction Management
  • , Measures implemented to prevent spread of Alien Invasive Species during construction.Environment Ecology
  • , Noise and vibration limited to BS 5228-1:2009+A1:2014 and BS 5228-2:2009+A1:2014.Construction Management
  • , Off-carriageway parking for all construction traffic; no parking on public roads; keep road clean of debris; maintain litter-free site; control dust/noise emissions.Construction Management
  • , Construction hours restricted Mon-Fri 08:00-18:00, Sat 08:00-13:00; no work on Sundays/Bank Holidays.Construction Management