Aghada Generating Station Aghada
Planning application 05/1260
DecisionConditional grant
Decided27 April 2005
Application typePERMISSION
Source documents1
Site
What is on file
0refusal reasons0conditions8nearby records
Proposed development
Application description published by Cork County Council.Application and appeal history
Structured appeal stages, outcomes and source documents currently tied to this application.No indexed appeal history
No structured appeal case is tied to this application. This means no appeal is indexed, not that an appeal is impossible.
Decision details
Core application dates and identifiers from the public planning record.Planning analysis
Refusal reasons and planning conditions extracted from the public decision file.Refusal reasons
No refusal reason on record
Documents are indexed. Reason extraction for Cork has not started yet.
Conditions
No conditions
No conditions are on record for this application yet.
Planning a project near Aghada Generating Station Aghada?
Get a site risk brief with the local decision pattern and up to 80 detailed nearby comparables (40 refusals and 40 grants), including extracted reasons and source links. €29 incl. VAT, PDF by email.Source documents
Original council portal records and source PDFs where available.Nearby precedent
Similar nearby applications linked to this planning decision.- 04/5913A combined cycle gas turbine (CCGT) power plant, with an output of 380 - 450MW, The development will consist of a gas turbine, heat recovery steam generator; one exhaust stack of up to 70m in height, one by-pass stack of up to 50m high, steam turbine, workshops and stores, control and administration building, water treatment plant, cooling water pumphouse, 440m long submerged sea cooling water outfall pipe with elevated platform at the discharge point, electrochlorination plant, auxiliary boiler with 48m high stack, gas compressor, minor ancillary buildings, two oil tanks of up to 20m in height, three water tanks of up to 15m in height, electrical equipment, transformers, gas compound, sewage treatment plant, miscellaneous plant and equipment, site development, landscaping and fencing. The planning application includes 2 different design options / 0.0 km away / 23 September 2004Granted
- 11/5408Single storey store building / 0.2 km away / 11 November 2011Granted
- 24/4026The proposed development consists of the construction of a hydrogen production facility comprising a hydrogen compound and contractor’s compound with all associated site access and ancillary site development works. The proposed development will demonstrate the full chain hydrogen production via electrolysis, storage, usage on site via fuel cell and transport offsite to other sector hydrogen users. The proposed development is to be used for hydrogen production for an operational period of up to five years. The proposed development comprises: 1) 1 megawatt (MW) electrolyser including a water purification unit (40-foot (ft) container) (2.5m x 12.2m x 5.4m) with a stack height of 7.7m above ground level, 2) A transformer and control unit container (2.8m x 7.5m x 3.3m) housing a 6.6 kilovolt (kV) to 400kV transformer, 3) A storage container (2.8m x 6.4m x 3.3m), 4) A welfare unit (2.8m x 7.5m x 3.3m), 5) A compressor (20ft container) (2.7m x 6.4m x 4.3m), 6) 5 x 2.5kg low pressure (30 bar) hydrogen storage MCP units (manifolded cylinder pallets) (1m x 1m x 2.1m), 7) 3 x 19kg high pressure (300 bar) hydrogen storage MCP units (manifolded cylinder pallets) (1m x 1m x 2.1m), 8) 2 x 61kg low pressure (30 bar) nitrogen storage MCP units (manifolded cylinder pallets) (1m x 1m x 2.1m), 9) 2 x 31kg high pressure (300 bar) nitrogen storage MCP units (manifolded cylinder pallets) (1m x 1m x 2.1m), 10) 4 x 400kg (high pressure) mobile refuelling hydrogen storage vehicles, 11) 2 x 250 kilowatt (kW) hydrogen power units (2.7m x 7.3m x 5.4m), 12) Heavy goods vehicles (HGV) loading bays with 4m high walls, 13) A palisade fence enclosing the hydrogen compound (2.6m height). In addition to the above, planning permission is also sought for all ancillary site and development works to facilitate the development including the MCP filling area, internal site access road, 3 no. car parking spaces, 2 no. EV chargers, barrier, lighting and CCTV, drainage infrastructure and pipe racks/cable trays. After up to five years in operation, the decommissioning phase of the proposed development will comprise the removal of the electrolyser, transformer and control unit container, compressor, MCP units, mobile refuelling hydrogen storage vehicles, hydrogen power units, storage container and welfare unit from the site and removal of loading bay walls to level in line with the concrete yard. The contractors compound area will be reinstated to its present condition during decommissioning. It is proposed that all utility service connections and all other structures and installations on site including, but not limited to, the hydrogen compound fencing, concrete yard, lighting and CCTV will be retained on site in perpetuity. The proposed development consists of an activity for which an Industrial Emissions Licence is required. ESB Aghada Generating Station is a registered lower tier establishment under the Control of Major Accident Hazard (COMAH) Regulations, 2015. The development will consist of the provision of, or modifications to, an establishment within the meaning of Part 11 of the Planning and Development Regulations (Major Accidents Directive). A Natura Impact Statement (NIS) will be submitted to the planning authority with the application. / 0.2 km away / 05 March 2024Granted
- 07/10507Construction of 220kV switching station (tail station) compound comprising of surge arrestors, voltage transformers, line earth disconnects, circuit breaker, single storey control building, site roads, entrance gate and fencing / 0.3 km away / 18 October 2007Granted
- 23/5104Development is sought for a period of 10 years at a 10.22 hectares site within ESB Aghada Generating Station consisting of 1) Construction/installation of an open cycle gas turbine (OCGT) generating unit and associated plant and equipment, comprising the following main components with approximate dimensions as stated: Gas turbine air intake [24m x 18m x 26m high], Generator enclosure [24m x 18m x 14.5m high], Gas turbine enclosure [53m x 15m x 26m high], Exhauster diffuser [14.5m x 10.4m x 10.5m high], Exhaust stack [40m high, 8m diameter], Gas turbine control and electrical modules [20.5m x 18m x 10m high], Fin fan coolers [27m x 19m x 8m high], Main transformer [12.2m x 7.5m x 8.5m high] including 17.6m x 17.9m concrete bund; and 2 no. 12m high concrete blast walls, Auxiliary transformer [5m x 4.7m x 7.5m high] including 6.8m x 7.5m concrete bund; and 2 no. 12m high concrete blast walls, Demineralised water treatment plant [20m x 10m x 5.4m high], Demin water storage tank [14.63m high x 24.4m diameter], Raw water/Firewater storage tank [14.63m high x 15.2m diameter], Fuel oil storage tanks [two, each 12.19m high x 17.4, diameter], including 67m x 35m concrete bund, Fuel oil forwarding pumps [6m x 10m x 2.2m high], Firefighting pumphouse [10m x 7m x 5.4m high], Gas conditioning compound [42.3m x 11.5m x 6m high]. Above ground installation gas compound expansion [23m x 73m], Indoor switchgear building [20m x 30m x 18m high], Emergency diesel generator <1 MW [10m x 4m x 5m high], Generator circuit breaker [8.8m x 5.1m x 4m high], Continuous emissions monitoring skid [3.5 m x 2.5m x 5m high], Workshop/Stores/Administration building [35.9m x 12m x 15m], Hydrogen storage compound [8m x 4m x 2m high], Surface water drainage system, Vehicle parking, Internal roadways, 2) Demolition of an existing single storey stores building, 3) connection to the existing on-site above ground installation (AGI), 4) Connection to the National Grid by means of underground cable to existing on-site 220kV substation, 5) All associated works to facilitate the development such as temporary construction compounds, perimeter fencing, use of an existing access to public road, above ground pipe racks, underground cables on the site and crossing the R630 roadway, site lighting and telecommunications. The development consists of an activity for which an Industrial Emissions Licence is required. ESB Aghada Generating Station is a registered lower tier establishment under the Control of Ma / 0.3 km away / 02 November 2023Granted
- 20/6011Permission for development on a 1.81 ha site which is licenced by the Environmental Protection Agency under an Industrial Emissions (IE) Licence (Ref. P0561-05) and a Lower Tier COMAH site and therefore falls under the requirements of the control of Major Accident Hazard Regulations (COMAH) Regulations, 2015. The development will consist of a 75 MWe (electrical output) aero derivative gas fired turbine, including the following elements: (a) 1 No. turbine module (c.535 sq.m., c.15.2m high) in a fully enclosed weatherproof acoustic enclosure including a c.30m high stack, selective catalytic reduction (SCR), gas turbine and air intake; (b) supporting items of plant including: step up transformer with firewall (c.192 sq.m.); bunded station service transformer (c.11 sq.m); single storey control/electrical room (c.150 sq.m.); bunded ammonia storage tank (c.20 sq.m.); gas compressor (c.128sq.m.); gas compressor cooler (c.28 sq.m.); single storey building containing a fire suppression system and gas bottle storage (c.79 sq.m.); fin fan coolers (c.53 sq.m.); lube oil skid (c.32 sq.m.); fenced gas receiving station (c.11 sq.m.); (c) external service areas including a maintenance laydown area and an ammonia unloading area; (d) connections to existing site services networks including gas, liquid fuel, electrical, water and wastewater and an underground surface water attenuation tank connecting to surface water drains; (e) all other ancillary and miscellaneous site works including site clearance; site access and a temporary construction compound. [For information – the planning application represents a resubmission of a similar 55MW development approved by CCC under Reg. Ref. 19/05411]. The planning permission is being sought for a 10 year duration. The application relates to a development which comprises or is for the purposes of an activity requiring an Industrial Emissions Directive (IED) licence and full details of the proposed development and its anticipated environmental impacts will be notified to the Environmental Protection Agency (EPA). A Natura Impact Statement (NIS) will be submitted to the Planning Authority with the application. / 0.4 km away / 10 November 2020Granted
- 19/5411A 55 MWe (electrical output) aero derivative gas fired turbine, including the following elements: (a) 1 No. Turbine module (c.535 sq.m., c.15.2m high) in a fully enclosed weatherproof acoustic enclosure including a c.30m high stack, selective catalytic reduction (SCR), gas turbine and air intake; (b) supporting items of plant including: step up transformer with firewall (c.192 sq. m.); bunded station service transformer (c.11 sq. m.); single storey control/electrical room (c.150 sq. m.); bunded ammonia storage tank (c.20 sq. m.); gas compressor (c.128 sq. m); gas compressor cooler (c.28 sq. m.); single storey building containing a fire suppression system and gas bottle storage (c.79 sq. m.); fin fan coolers (c.53 sq. m.); lube oil skid (c.32 sq. m.); fenced gas receiving station (c.11 sq. m.); (c) external service areas including a maintenance laydown area and an ammonia unloading area; (d) connections to existing site services networks including: gas, liquid fuel, electrical, water, wastewater, and an underground surface water attenuation tank connecting to surface water drains; (e) all other ancillary and miscellaneous site works including site clearance; site access and a temporary construction compound. Planning permission is being sought for a duration of 10 years. The application relates to a development which comprises or is for the purposes of an activity requiring an Industrial Emissions Directive (IED) licence and full details of the proposed development and its anticipated environmental impacts will be notified to the Environmental Protection Agency (EPA). A Natura Impact Statement (NIS) will be submitted to the Planning Authority with the application. A 1.81 ha site located to the east of the R630; located inside the Aghada Generating Station, which is licenced by the Environmental Protection Agency under an Industrial Emissions (IE) Licence [Ref.P0561-05] and a Lower Tier COMAH site and therefore falls under the requirements of the Control of Major Accident Hazard Regulations (COMAH) Regulations, 2015. / 0.4 km away / 02 October 2019Granted
- 18/5659The development of a c.19 MW capacity battery storage facility located within a secured compound, on a 0.65 Ha site, and will –subject to detailed design, commercial and technical considerations; include; (a) up to 6 No. battery storage units [each typically comprising a containerised battery (c.12.2m x 2.5m x 3.2m), HVAC (c2.7m x 2.7m), inverter (c.3m x 3m) and transformer (c.3.3m x 3.3m)]; (b) a 28sq.m single storey control equipment building; (c) a 28 sq.m single storey switchgear building; (d) ancillary electrical plant including a transformer and var support unit; (e) a c.15.6m high lightning mast and c.18m high SCADA communications mast; (f) a 2.6m high chainlink fence and access gate, with primary access via the existing station and temporary access via the existing boundary onto the R630; (g) ancillary site works including site clearance and the installation of site services. Licenced by the Environmental Protection Agency under an Industrial Emissions (IE) Licence [Ref. P0561-05] and a Lower Tier COMAH site and therefore falls under the requirements of the Control of Major Accident Hazard Regulations (COMAH) Regulations, 2015. / 0.4 km away / 20 August 2018Granted