GrantedDecided 23 September 2020Fingal County Council

FW19A/0232: The construction of a Data Centre comprised of 4 no. buildings consisting of (a) Data Hall Building, (48,303 sq.m) 4 storey building with plant room over (b) Generator Building, (4,064 sq.m) 4 storey building over a single basement level, (c) Sprinkler Pump House building, (119 sq m.) single storey building, and (d) Security Hut, (21 sq.m.) single storey building with associated security barrier system, and the formation of a new vehicular entrance onto Damastown Avenue, 102 no. car parking spaces including 6 no. disabled car parking spaces, 30 no. cycle spaces, internal site roads and hardstanding, site lighting, perimeter security fencing and gates, site signage, soft landscaping, SUDS drainage system, and all other associated site works, on a 2.6709 hectare site at Damastown Avenue, Damastown Industrial Park, Macetown Middle, Mulhuddart, Dublin 15. Additional Information Lodged on 22nd May 2020 Clarification of Add Info received 27th August 2020

Damastown Avenue, Damastown Industrial Park, Macetown Middle, Mulhudda
DecisionGrant permission
Decided23 September 2020
Application typePermission
Source documents20

Site

What is on file

0refusal reasons0conditions8nearby records

Decision details

Core application dates and identifiers from the public planning record.

Planning analysis

Refusal reasons and planning conditions extracted from the public decision file.

Refusal reasons

No refusal reason on record

Documents are indexed. Reason extraction for Fingal is in progress.

Conditions

No conditions

No conditions are on record for this application yet.

Planning a project near Damastown Avenue, Damastown Industrial Park, Macetown Middle, Mulhudda?

Get the precedent report for this site: every grant and refusal within 5 km, and the planners' reasons. €49 incl. VAT, PDF by email.

Source documents

Original council portal records and source PDFs where available.

Nearby precedent

Similar nearby applications linked to this planning decision.
Full reasons for every nearby decision are in the site report →