SD25A/0220W: The installation of Solar PV Panels to be mounted on the rooftop of an existing warehouse building and all associated ancillary infrastructure. PV Panels will not extend above parapet line.
Block 506, Units 1 & 2, Collegeland, Greenoge, Greenogue Business Park, Rathcoole, Co. Dublin
DecisionGrant permission
Decided11 November 2025
Application typePermission
Source documents1
Site
What is on file
0refusal reasons0conditions8nearby records
Decision details
Core application dates and identifiers from the public planning record.Planning analysis
Refusal reasons and planning conditions extracted from the public decision file.Refusal reasons
No refusal reason on record
Documents are indexed. Reason extraction for South Dublin has not started yet.
Conditions
No conditions
No conditions are on record for this application yet.
Source documents
Original council portal records and source PDFs where available.Nearby precedent
Similar nearby applications linked to this planning decision.- SD08A/0550Retention of a mains pressure tank for fire fighting at Units 506 & 508 of permission SD03A/0066. This tank is a requirement of the Fire Certificate. / 0.0 km away / 01 October 2008Granted
- SD05A/0724Revisions to the permitted unit 506 & 508 of permission SD03A/0066, a planning permission which allowed for industrial /warehousing units in 20 blocks including 17,298 sq.m of office accomodation and all associated site works and the demolition of existing house and to allow for amalgalation of sites for permitted units 506 & 508 and that sites development to provide for one overall building that amalgamates the permitted floor space of units 506 & 508: the new building and site layout will provide for four seperate internal warehouse units to be developed an a phased basis, revisions to the permitted site layout, landscaping parking access and circulation arrangements: the propsed development allows for an increase in the combined area of floor space permitted for units 506& 508 from 19,887 sq.m to 20,298 sq.m in the new development: the revised layout amalgamating the area of units 506 & 508 will provide for a total of 16,775 sq.m of warehouse space (a reduction from 16,996 sq.m in the orignally permitted units 506 & 508) and a total of 3,523 sq.m and ancillary office space ( an increase from 2,881 sq.m in the originally permitted unit 506 & 508); other alterations include a change from the general location of the building footprints of the permitted units 506 & 508 to the propsed location of the new structure, revised building elevations, provision of vehicle wash, maintance and fueling facilities for HGV's using the development and other ancillary developments and site development works: all development will take place at the townland of Greenogue, Co Dublin on an overall site of 8.4 acres. / 0.1 km away / 21 December 2005Granted
- SD07A/0022Internal re-plan of offices, repositioning external doors and windows to suit; removal of external drivers waiting/reporting pods; changes to total loading dock numbers from 25 no. to 24 no; relocation of MHE access ramp and door to Unit 1; removal of 1 no. waste compactor; redistribution of silver-metallic coloured feature strips; minor reproportion of external glazing / curtain walling; small increase to building height of 0.172m; 0.3m reduction in FFL from 90.1m OS to 89.8m OS; reduction in building length by approximately 0.6m; minor increases to width of building; reduction of constructed mezzanine from 15m to 7.5m wide, allowing for expansion in the future; removal of 1 no. fuel and wash facility, leaving 1 no. facility; removal of 2 no. external cat-ladder roof access and introduction of roof lights and access hatches. / 0.1 km away / 02 March 2007Granted
- SD10A/0283Construction of a 4.5 MW geothermal electricity generation plant comprising a 9.5m high, 675sq.m. building; 2 x 4000m deep wells (production and injection); 3.51m high, 110sq.m. enclosure; external air cooling fans; underground water attenuation tank; 8 no. car parking spaces; formation of a new vehicular access and ancillary works including the erection of a 2.5m high boundary paladin fence; paving; hydrocarbon interceptor; ESB compound (2.6m high, 9sq.m.) and site development works within a planning application area of 3.5ha on a site previously granted planning permisison for 2 no. light industrial buildings (Register Reference SD07A/0580). Temporary construciton phase works to consist of a 42m high drilling rig mounted on a working pad, drilling mud circulation system (including an attenuation pond and drill cuttings storage area), covered water tank, 4 no. diesel generators, bunded diesel storage tank, cement silos; containerised compound for offices, canteen, workshops and portaloo toilets. An Environmental Impact Statement has been submitted in connection with this application. / 0.1 km away / 17 November 2010Granted
- SD21A/0111Construction of a double height (8.5m high) industrial warehouse building for plant machinery maintenance and storage purposes; associated ancillary two storey office and staff welfare accommodation (c.501sqm Total GFA); 9 car parking spaces, 3 bicycle parking spaces and all associated site ancillary development works and drainage connections. / 0.1 km away / 21 September 2021Granted
- SD05A/0012Revised site plan, building footprint, floor plans & elevations comprising the construction of 1 no. block of warehousing unit, (8.65m high, previously 11.40m) totalling 400m.sq. (previously 1079m.sq.) together with 2405m.sq. yard to side/rear at previously approved site 509 (Reg. Ref. SD03A/0066 - PL.06S.204281) / 0.1 km away / 28 February 2005Granted
- SD07A/1006Alteration to an existing granted planning application (Reg. Ref. SD07A/0074 and SD07A/0430) comprising revision to plans, elevations, site plan, building footprint, entrances, car parking, paving, landscaping and site development works. This revised application comprises 135sq.m. total area, 3 no. warehousing/light industrial units in 1 no. block comprising 240sq.m. integrated ancillary office accommodation, 117sq.m. staff facilities, 308sq.m. mezzanine storage and 697sq.m. of warehousing, 11.85m high overall. (Previously 1,224sq.m. total area, 2 no. warehousing units in 1 no. block including 209sq.m. integrated ancillary office accommodation 11.8m high). / 0.1 km away / 18 February 2008Granted
- SD07A/00742 No. warehousing units totaling 1,094m.sq (11.85m high) consisting of the following Unit A totaling 539m.sq including 107m.sq of ancillary office on 2 floors, 23m.sq of staff facilities on 2 floors and 409m.sq of warehousing on 2 floors. Unit B totaling 555m.sq including 102m.sq of ancillary office on 2 floors, 116m.sq of staff facilities on 2 floors and 337m.sq of warehousing on ground together with services, utilities, boundary fences, landscaping, planting, paving, parking and associated site development works. / 0.1 km away / 28 March 2007Granted