Applications tied to the site
Partial coverage2 register records are within the point-match tolerance; a parcel boundary is needed to treat this as exact.
2 matchedSite planning risk brief
One-off house / within 5 km where a location match is available
Executive snapshot
4% of nearby decided applications were refused. The site check found 321 decisions within 5 km, 2 exact-site or onsite candidate records, and 11 structured appeals.
Evidence maturity
Each section reports its own coverage. “Not yet covered” means no conclusion is drawn while source datasets or policy extraction are still being loaded.
2 register records are within the point-match tolerance; a parcel boundary is needed to treat this as exact.
2 matchedCurrent indexed zoning and settlement layers are intersected with the selected site where coverage exists.
Current section-and-page citations have not yet been loaded for this authority.
Each layer reports its own coverage; missing coverage never appears as a clean result.
0 prompts are backed by extracted nearby decision evidence; all prompts remain checks, not predictions.
11 structured nearby appeal records.
11 matchedHistoric extracted references are not presented as current policy; verified citations are still being loaded.
Open preview
Open preview
The development will consist of the extension of the operational lifespan of a solar farm permitted by Carlow County Council under Planning Reg. 22/118 from 35 No. years as permitted (by reason of condition No. 3 of permission Planning Reg. 22/118) to 40 No. years.
The proposed works will include a solar farm on an area of approximately 14.16 hectares, comprising photovoltaic panels on ground mounted frames, 4 no. single storey inverter/transformer stations, 1 no. single storey terminal stations, 1 no. single storey electrical switch room, 1 no. storage container, security fencing, CCTV and all associated ancillary development works. Elgin Energy Services Ltd. are applying for the proposed solar farm to have planning permission that is effective for 10 years (and an operation period of 40 years)
The development will consist of the relocation and revised design of a single storey medium voltage electrical substation (previously permitted as part of a solar farm permission by Carlow County Council Planning Reg. 22/118) to provide a revised single storey 20kV substation building at a revised location within the overall permitted solar farm site. The application also seeks permission for a turning area adjacent to the proposed substation to accommodate emergency fire tender access and revisions to the permitted solar panel layout to accommodate the relocated substation and proposed turning area.
The construction of a dormer-style extension to side of existing dwelling, the decommissioning of existing septic tank and installation of new onsite wastewater treatment system with polishing filter, along with all associated site development works
To install an agricultural field entrance and associated works
For the continued use of the existing 30m high communication structure carrying antennae and dished with all associated ground-mounted equipment, within an existing 2.4m high palisade compound following on from previous LPA ref no. 10/208
The brief summarizes the pattern across all 321 matched decisions within 5 km and includes up to 80 detailed comparables (40 nearest refusals and 40 nearest grants), with extracted reasons, quotes, and available source links. €29 incl. VAT.
Source match
Matched from public planning record 22118The site brief adds up to 80 nearest detailed grants and refusals, extracted source evidence, document links, and a shareable risk summary.
Included in site brief
Included in site brief
Included in site brief
Included in site brief