  1. © OpenStreetMap
    2561104Granted

    Main Street R125 Ballybin Road, Ratoath, Co Meath

    Amendments to the ‘Large-Scale Residential Development’ (LRD) permitted at a site under Reg. Ref. 24/60487 / ABP Ref. 321753-25. The LRD site has a total area of 5.48 hectares and is principally located at. The total site contains a permitted residential and creche development site with an area of 3.66 hectares (bisected by a proposed realigned Ballybin Road) and a permitted infrastructural development site with an area of 1.82 hectares (principally for road and related works, water services and open space amalgamation). The site is generally bound by: Fox Lodge Woods and Fox Lodge Manor to the west and north; existing agricultural lands and residential development to the north and east; existing Ballybin Road and Moulden Bridge to the east; and Main Street/R125 and Jamestown Road/L1016 to the south. The site also incorporates parts of: the existing Ballybin Road (north and west of Moulden Bridge), Main Street/R125, Jamestown Road/L1016 and green open space in Fox Lodge Manor. The proposed amendments are limited to a 0.37-hectare portion of the LRD site, located between the permitted realigned Ballybin Road (west and north), greenway (i.e. existing Ballybin Road, east) and Main Street/R125 (south). Development description: The proposed development principally consists of amendments to the design of 2 No. permitted houses (specifically types X1 and X2). The permitted part-1-/part-2-storey (with habitable attic), 5-bedroom X1 house (225.4 sq m) is to be amended as a part-1-/part-2-storey, 4-bedroom house (278 sq m). The permitted part-1-/part-2-storey (with habitable attic), 4-bedroom X2 house (225.4 sq m) is to be amended as a part-1-/part-2-storey, 5-bedroom house (278 sq m). The amendments involve changes to the houses’ external and internal designs and layouts. Other proposed amendments include: associated changes to the site layout and landscaping to accommodate the above house changes; changes to the permitted boundary treatments enclosing and between the 2 No. houses; alterations to the permitted vehicular entrances serving the 2 No. houses; and all other associated site and development works above and below ground to facilitate the amendments. (Note: details below for floor areas, unit types, car parking, etc. relate to the proposed units subject to this amendment.)Decision record indexed
    Decision04 December 2025View record
  2. © OpenStreetMap
    WEB5350/25Granted

    Rear of 34 North Circular Road, Dublin 7, and Fronting O'Devaney Gardens, D08RF3F

    The development will consist of: (i) the removal of existing boundary wall and vehicular gate fronting the mews lane; (ii) the construction of a three-storey mews building fronting O’Devaney /gardens containing 3 no. units, consisting of 2 no. 1 bed apartments and 1 no. studio apartment. 1 no. unit is provided per floor level; (iii) the provision of an outdoor terrace to rear at ground floor level, and provision of balconies to the front elevation at first & second floor levels; (iv) the provision rooflights to the main roof at second floor level; (v) the provision of bin stores and bicycle storage; and (vi) landscaping, boundary treatments, SuDS and new foul drainage connection, and all other ancillary works necessary to facilitate the development.Decision record indexed
    Decision02 December 2025View record
  3. © OpenStreetMap
    WEB5345/25Refused

    Cranford, 125 Rathgar Road, Rathgar, Dublin, D06 W2C3

    PROTECTED STRUCTURE: a) the demolition of the existing garden shed to the rear of the existing annexe building to the side (North) of the main house b) the refurbishment of the existing annexe building to include an apex rooflight and roof mounted solar panels c) a two storey high brick extension to the rear (East) of the annexe building connected to the existing annexe with a two storey glazed link all to accommodate living space and a screened roof garden at first floor level, two bedrooms a study, bathrooms, a shed and a covered bike store at ground floor level within the curtilage of Cranford, 125 Rathgar Road, Rathgar, Dublin 6, D06 W2C3, a protected structure. The development will include all associated landscaping, drainage and site development works.Grounds not yet categorised
    Decision01 December 2025View record
  4. © OpenStreetMap
    2560624Granted

    No.3 Highland View Terrace & The Cottage, Fairgreen, Naas

    For an extension comprising a mixed use development of office & apartments. The development will consist of: A) Demolition of Single Storey House (73m2) at The Cottage, Fairgreen, Naas Co. Kildare (W91 NXR7); B) Partial demolition of existing single storey extension to rear and Internal modifications and alterations to existing offices at No. 3 Highland View Terrace C) Construction of a two storey Dormer extension on north side of the existing offices facing the main street with dormer style windows to pitched roofs and comprises of proposed office accommodation at ground, first & second floor level (Total floor area= 250m2), two storey covered stairway and walkway in centre of proposed building and a two storey Dormer /three-storey building to rear comprising office accommodation at ground floor level (floor area = 100m2) and 1 no. 2-bedroom apartment on first & second floor levels (floor area = 92m2 each apartment). Each apartment will have private amenity space provided by an inset balcony. D) Secure cycle parking and bin storage will be located to the rear of the mixed-use development; new railings and pedestrian gate to match existing at front boundary, with hard landscaping area to front set-back; hard & soft landscaping to rear courtyards & open spaces. E) Ancillary site development works that include the installation of pipes & connections to the existing public sewage system & water supply, new soakaway and all associated works. Revised by Significant Further Information which consists of: revised site layout, revisions to building line to front and rear, revised courtyard and communal space arrangements, details of proposed finishes, landscape designs, submission of additional reports including bat survey, tree survey and sunlight analysis and construction management planDecision record indexed
    Decision28 November 2025View record
  5. © OpenStreetMap
    24/6272Granted

    Corracunna, Coolnanave Garrane Mitchelstown Co. Cork

    The application site comprises an area of c. 5.61hectares. The site is primarily located in the townland of Corracunna and is surrounded by agricultural lands to the North and East, with the N73 national route to the south, and the L90813 local road to the west. The site takes in lands at Coolnanave and Garrane, on the western side of the L90813, to the west and north west of the main site area, to provide woodland planting and an underground drainage pipe and outfall. The proposed development comprises the construction of an anaerobic digestion facility to produce renewable biomethane, CO2 (which will be captured) and a bio-based fertiliser from organic material. The total proposed gross floor area of the development (including internal plant areas and ancillary structures) will be c. 3,419.5 sq.m. Permission for the; (1) Demolition of existing single storey disused agricultural buildings, silos, and tank within the western portion of the site (total demolition gross floor area (GFA) of c. 1,781 sq.m). One single storey agricultural building (with GFA of c. 87.8 sq.m and height of c. 5.1m) will be stabilised and retained as a biodiversity building. (2) Construction of 3 no. digesters (c.15.6m in height), 2 no. digestates storage structures (c. 15.5m and 11m in height), 2 no. liquid storage tanks (c.12.2m in height) and a liquid feed tank (c. 8m in height), located in the southeast portion of the site. (3) 3 no. pasteurisation tanks (each c. 6m in height), a post-pasteurisation cooling tank (c.12.2m in height) and pre fertiliser manufacturing tank (c.12.2m in height), located in the centre of the site. (4) part single-storey and part two-storey reception hall (with a GFA of c. 2,112.6 sq.m and an overall height of c. 15.5m) to accommodate a laboratory, panel room, tool store, workshop, and storage areas, with a liquid feed intake adjacent to the reception hall, located in the central portion of the site, to the north of the digesters. (5) a single-storey solid digestate storage and nutrient recovery building (with a GFA of c. 879.9 sq.m and a overall height of c.12.4 in height) will be located to the west of the reception hall, in the central portion of the site. (6) Odour abatement plant (with a maximum height of c. 6m in height) and equipment, a digestate offtake area, and a fuel tank (c. 1.6 in height) will be provided to the north of the solid digestate storage and nutrient recovery building. (7) Construction of an ESB substation (c. 3.4m in height) 2 no. CO2 tanks and a CO2 loading pump (c. 14.5m in height), along with associated plant structures including CO2 auxiliaries, CO2 liqueufactor, a CO2 compressor and a CO2 pre-treatment skid (with an overall height of c. 6.7m), located in the southwest portion of the site. (8) Construction of a biogas treatment skid, a biogas compression system, a biogas upgrading module (with an overall height of c. 5.1m) and a grid injection unit within a fenced compound (c. 2.8m in height), located within the southwestern portion of the site. (9) Construction of an emergency biogas flare (c. 11.3m in height) 2 no. propane tanks (c. 1.3m in height) and a grid off take skid, located further to the west of the site. (10) Construction of O2 generation unit (c. 2.6m in height), a biomethane boiler (c. 5.6m to top of flue stack), a combined heat and power (CHP) unit and panel room (with a maximum height of c. 6m to top of flue), 2 no. pump houses (c. 2.6m in height, each with a GFA of c. 29sq.m) located in the southwestern portion of the site, south of biogas upgrading structures. (11) Construction of a two-storey ancillary office and administration building (with an overall height of c. 8.6m and GFA of c. 271.5 sq.m), located within the western portion of the site, adjacent to the main site entrance. (12) A discharge pipe route extending to the northwest of the main anaerobic digestion facility site, crossing the L90813 and through agricultural lands to the River Funshion. (13) Alterations to theDecision record indexed
    Decision27 November 2025View record
  6. © OpenStreetMap
    2561456Granted

    Drumgriffin, Corrandulla, Co.Galway

    For the 1. demolition of ground floor and 1st floor area to the rear of the house. 2. Construction of ground floor and 1st floor extension to the rear of the house. 3. Construction of a single storey link corridor on the north west elevation between the main house and the existing outbuilding. 4. Replacement of the existing roof and raising overall height, including raising the walls of the house and building new window opes as shown on plans. 5. Raising the rood on the existing porch on the front (north east) elevation including the construction of a new flat roof over. 6. Construction of a treatment system and percolation area and all associated site worksDecision record indexed
    Decision27 November 2025View record
  7. © OpenStreetMap
    2560482Granted

    Delvin Road Springfield, Mullingar, Co. Westmeath

    Of extension and alterations to Primary Care Unit (previously Nurse’s Home) which is a protected structure (RPS number: 019-224) to change use to office space for HSE Staff. The proposed works will consist of the removal of an existing plant room, and the construction of a new 135 sq. m. three-storey extension on the north side to provide stairs and lift access to the existing building at first and second floor level. Additionally, there will be general refurbishment, and reconfiguration works covering the total area of 1360 sq. m. on all three levels of the main building, along with a surface level car park with 26 spaces to rear of the building on the west side, an entrance canopy and associated site worksDecision record indexed
    Decision26 November 2025View record
  8. © OpenStreetMap
    25/6082Granted

    77, North Main Street, Youghal, Cork, P36W528

    Permission for material change of use of part of first floor from commercial space to create 1 bed flat. Change of internal layout previously approved under 24/5899, from 3 bed flat to 2 bed flat, including minor changes to windows to rear at 77 North Main Street, Youghal, a protected structure.Decision record indexed
    Decision25 November 2025View record
  9. © OpenStreetMap
    2560373Granted

    13-17 Seatown, Dundalk, Co. Louth

    The development will consist of the following: 1) Change of use of the existing premises from public house with associated first floor accommodation to 4 no. two storey townhouses, 1 no. first floor studio apartment, all with own door access and ground floor commercial unit. Provision of associated rear gardens, landscaping, fence enclosures, storage sheds, cycles spaces, drainage, private open spaces. The existing height of the premises is 2 storeys and will include minor demolitions as part of the works. 2) Alterations to include single storey rear extension for the townhouses, new rear facing rooflights and minor alterations to the main facades facing Seatown and Mary Street North.Decision record indexed
    Decision07 November 2025View record
  10. © OpenStreetMap
    2560282Granted

    Nua Manufacturing, O’ Brien Road, Co. Carlow

    A pedestrian gate to boundary fence at main entrance (Dr Cullen Road Roundabout) and extension of footpath, 2 no. access doors and 2 no. ramps to northern facade of factory, detached storage building (795m2) to the north of the factory with roof solar panels and external battery kiosk / invertor, single storey extension (100m2) to the east of the factory, single storey extension (1902m2) to the south of the factory with roof solar panels and external battery kiosk / invertor, detached storage building (1200m2) to the south of the factory with roof solar panels and external battery kiosk / invertor, refurbishment of existing factory (1001m2) and single storey extension (561m2) to the south, 12 no. cycle parking spaces and 4 no. EV parking spaces to the car park and all associated site development works16 conditions indexed
    Decision07 November 2025View record
  11. © OpenStreetMap
    2560957Granted

    Carranstown and Caulstown, Platin Duleek, Co. Meath

    The proposed amendments include: 1) Removal of the gas turbine buildings housing the approved OCGT units (Turbines, generators and auxiliary equipment). The OCGT units will remain in place; 2) Addition of FinFan cooler unit and associated plant; 3) Revised Water Treatment Plant (‘WTP’) design and layout, incorporating: Replacement of de-ionising building with modular demineralised water plant; Addition of air compressor container, waste water and oily water collection sumps, and chemical dosing skid; Revised position for chemical storage area and bund; Replacement of firefighting water tank with firefighting foam tank. 4) Addition of raw water and demineralised water pumps within water storage area; 5) Reduction in height and area of Service Building, from 6m high to 3m high and from 520 sq. m. to 256 sq. m.; 6) Revised positioning of Hydrotreated Vegetable Oil (‘HVO’) storage tanks within approved fuel storage area; 7) Addition of gas Above Ground Installation (‘AGI’) and connection to gas main running to the north of the site to facilitate the use of gas as a fuel option for the approved OCGT units. Electrical output will increase from 170MW to 190MW when fuelled on gas; 8) Addition of gas filtration, heating and pressure reduction skids; 9) Change in height of 110kV transformers, from 5m to 6.8m; 10) Addition of 4 no. auxiliary transformers; 11) Modularisation of switchgear building, resulting in revised area (Increase from 160.43 sq. m. to 225.20 sq. m.); 12) Addition of emergency generator; 13) All associated ancillary development, site works and services. The application relates to a development which comprises or is for the purposes of an activity requiring an Industrial Emissions Directive (IED) licence. The application relates to the provision of an establishment to which the Chemicals Act (Control of Major Accident Hazards Involving Dangerous Substances) Regulations 2015 (S.I. 209 of 2015) apply. A Natura Impact Statement accompanies the application, which takes account of the proposed amendments and also additional minor development on the site (MV substation building and associated underground cabling) that has been applied for under a separate applicationDecision record indexed
    Decision04 November 2025View record
  12. © OpenStreetMap
    2560287Granted

    Colaiste Mhuire Urlingford Road, Warrenstown Johnstown, Co. Kilkenny

    For 1) The construction of a new standalone 3,879.1 sq.m extension. The building height varies from 1 to 2 storey. Accommodation provides for, 13 General Classrooms, 11 SET rooms, 2 Science Laboratories with associated preparation room, 1 home economics room, 1 Textile room, 1 Engineering room with associated prep room, 1 Art room with associated project store, 1 graphics room with associated project store, 1 Staff room, 1 kitchenette, 1 Library, 1 General purpose hall, ancillary accommodation and circulation. 2) Construction of a new access road, 2 No. delivery set down areas, 1 No. Maintenance set down area and a shared pedestrian and vehicular surface area, linking into the existing one-way system. 3) Relocation of 1 No. pedestrian crossing. 4) Construction of 64 No. cycle spaces and 17 No. car parking spaces. 5) New signage comprising of a wall mounted metal signage near the main building entrance. 6) Construction of foul pump station and soakaway 7) Construction of ESB substation and switch room 8) Relocation of 2 No. existing 2x1 tonne gas tanks to the north, removal of 1 No. 600kg gas tank and replace with 1 No. 1 tonne gas tank. 9) Construction of LPG, Bin store and heat pump compounds, 10) The removal of 3 No. existing prefabricated classrooms 11) All associated ancillary site development and landscaping worksDecision record indexed
    Decision04 November 2025View record
  13. © OpenStreetMap
    25174Granted

    Beechmount Industrial Estate, Townparks Navan, Co. Meath C15 TK54

    The development will consist of 1. Change of use of existing warehouse to retail showroom. 2. Existing building to be partly demolished to allow for vehicular access. 3. Modification and upgrading of elevations. 4. Tensile fabric awnings to installed above the windows and new main entrance. 5. New signage will be installed on 3 facades facing North-West, North-East, and South-East. 6. Internal refurbishment. 7. External landscaping and associated site worksDecision record indexed
    Decision31 October 2025View record
  14. © OpenStreetMap
    2460597Granted

    Woollen Mill, Derrybawn Laragh, Co. Wicklow

    (1) The completion of a 366.32 sqm first floor bedroom extension and roof to existing ground floor plan consisting of dining room, reception, sun lounge, toilets, store, lift & lobby to existing gnd. floor extension (works to involve construction of an upper storey & roof for the north-western extension & works required for the completion of the two-storey extension), car parking, connection to existing services & site ancillary works granted under planning permission reg. ref. no. 08/20 (all existing works on site are permitted works under ref. 08/20); (2) Amendments to permission reg. ref. 08/20 to incl. revised parking & access arrangements incl. construction of a car park & access road, incl. the felling of 17 no. trees (as permitted under ref. 08/20); (3) Tree planting & landscaping around the car park & throughout the site; (4) Decommissioning of an existing on-site wastewater treatment plant, & construction of a pressurised connection via a new 1.1 km rising main to an Uisce Eireann foul sewer for treatment in the Laragh public WWTP (route will cross woodland, agricultural land, the Glendasan River & pass to & along the R756 road to the foul sewer). Foul pumping station to be constructed adjacent to the existing WWTP, as well as 2 No. air vales and a scour valve chamber along the route; (5) Construction of surface water drains discharging to the Glendasan River; (6) Existing wellbore for connection to hotel; and (7) All associated works including service connections. The planning application is accompanied by a Natura Impact StatementDecision record indexed
    Decision29 October 2025View record
  15. © OpenStreetMap
    25/5784Granted

    Maine North, Newtownshandrum, Cork, P56YE02

    Permission for Retention of a two storey dwelling house, detached domestic garage and two no. vehicular entrances and Permission for the installation of a wastewater treatment plant and associated percolation area and Permission for a bored water well to serve the existing dwelling house.Decision record indexed
    Decision28 October 2025View record
  16. © OpenStreetMap
    2584Refused

    ELM GROVE, CLONOGHILL, BIRR CO. OFFALY

    THE CONSTRUCTION OF BOTH A SINGLE STOREY GATE LODGE & A GARDEN PAVILION FOR SPORTS ACTIVITIES TO THE WEST AND NORTH WEST RESPECTIVELY OF THE MAIN BUILDING, PROPOSED LANDSCAPING AND ALL ASSOCIATED SITE WORKS. THIS BUILDING IS WITHIN THE CURTILAGE OF A PROTECTED STRUCTURE UNDER THE RECORD OF PROTECTED STRUCTURES IN THE OFFALY COUNTY DEVELOPMENT PLAN 2021-2027 (RPS REF. 53-327).Grounds not yet categorised
    Decision24 October 2025View record
  17. © OpenStreetMap
    2460485Granted

    Coolderry Dromintobin North Dromintobin South Knockbrack Lower, Knockbrack Upper Monaskeha Oakfield and Ruanard (townlands), Ardnacrusha Co. Clare

    A 10-year planning permission for a solar array. The development will consist of c. 330,000 m2 of solar panels on ground mounted frames, 13 no. single storey control cabins with associated electrical transformer units and hardstand areas, 2 no. ring main units, underground cabling within the solar array site and within the R471 public road to connect solar array field parcels, security fencing, internal CCTV, access tracks (upgrade of existing and new), upgrade to 1 no. existing agricultural field entrance and creation of 2 no. new entrances on the R471 and 1 no. new entrance on the L70382, 2 no. temporary construction compounds (including site offices and welfare facilities), landscaping and all associated ancillary apparatus and development works. The proposed development provides for minor modifications to the solar array permitted under Clare County Council Reference P22/591 / An Bord Pleanála Reference ABP-316043-23. These modifications comprise the omission of 1 no. single storey control cabin and associated electrical transformer unit, omission of solar panels and access track, and reconfiguration of internal cabling. The solar array will connect to the national grid and will have an operational lifespan of 40 years. A Natura Impact Statement (NIS) has been prepared and will be submitted to the Planning Authority with the applicationDecision record indexed
    Decision16 October 2025View record
  18. © OpenStreetMap
    2560539Granted

    Athlumney Alexander Reid Ferganstown and Ballymacon, Navan, Co.Meath

    Permission for a Large-Scale Residential Development - The proposed development will consist of 223no. residential dwellings (26no. 1 -bed, 50no. 2-bed, 138no. 3-bed and 9no. 4-bed) and a crèche. The mix of residential units consists of 155no. houses (18no. 2-bed, 128no. 3-bed, 9no. 4-bed) and 68no. apartments (26no. 1-bed, 32no. 2-bed, 10no. 3-bed). Apartments are three to four storey simplex/duplex own door apartments arranged in 5no. blocks. All housing is two storey in height. The crèche is a two storey standalone building (c.443sq.m) with allocated car parking and set down area. The proposed development includes all associated site development works including reprofiling of the site, works to an existing drainage ditch, the construction of a temporary foul water pumping station and rising main, public lighting, three ESB substations, bin and bicycle storage structures, car parking and landscaping of open space. The proposed development also provides for connections both vehicular and pedestrian to the residential development by Meath County Council known as Gort Na Glaise including the culverting part of an existing drainage ditch, removal of part of an existing hedge and existing boundary walls constructed within the Gort Na Glaise development. Provision is also made for future pedestrian/cycle connectivity to the west in keeping with Masterplan MP12. The development includes pedestrian/cycle connections onto the LRD6 and will provide a pedestrian crossing point on Old Road to the south of the application site. The development will be accessed by extending a spur off an existing roundabout junction on the new LRD 6 distributor road to the north of the application site. A portion of this spur road was previously permitted under P.A. Ref. 21-1046/ABP-312746-22. The proposed development also provides for an additional vehicular/pedestrian access to connect to the main access road proposed as part of a development to the north / north-west of the application site under P.A. Ref. 24/60415 (currently on appeal to An Bord Pleanála ABP-322341-25). A footpath and cycle path will be constructed along the western side of the application site as part of this planning application to provide access to the new development. A natura impact statement (NIS) has been prepared in respect to the proposed development and will be submitted to the planning authority with the planning application. Significant further information/revised plans submitted on this applicationDecision record indexed
    Decision15 October 2025View record
  19. © OpenStreetMap
    2560946Granted

    Ballymore GAA, Bishopsland, Ballymore Eustace

    For: Low energy floodlights consisting of six number lamp standards 20m in height located around the main playing pitch. The installation of three number proprietary solar power generating car-ports 50.4sqm each to be located to north of tennis courts. The installation of 31sqm solar panel array to south facing roof of existing clubhouse. Ancillary facilities include 10 number bicycle parking standsDecision record indexed
    Decision13 October 2025View record
  20. © OpenStreetMap
    2560715Granted

    The Park Hotel, Kenmare, Co. Kerry

    • Demolition of an existing single storey timber building to the north-east of the site. • Development of a new single storey ‘Tigin’ building, comprising a multi-use space for small events, ancillary storage, kitchenette and W/C facilities, providing a total gross floor space of 147sqm, with the proposed ‘Tigin’ to be used be used for ancillary purposes to complement the existing facilities in the main hotel building • The proposed development includes all associated and ancillary works including landscaping and infrastructure works.Decision record indexed
    Decision10 October 2025View record
  21. © OpenStreetMap
    25/407Granted

    Newmills Rathbarry Rosscarbery Co. Cork. P85 AC63

    Construction of a one storey addition with skylights to the south-west side of the existing dwelling house, construction of a two storey addition with skylights to the rear north of the existing dwelling house with new flat roof over the existing portion of the dwelling house, alterations to existing dwelling including new proposed windows and doors to existing elevations, closing off the existing site entrance to the left of existing main site entrance and all associated site worksDecision record indexed
    Decision03 October 2025View record
  22. © OpenStreetMap
    SD25A/0129WGranted

    Former Agnelli Motors, Greenhills Road, Tallaght, Dublin, D24 PW77

    The development will consist of: (1) Permission for works comprising of: (i) Partial change of use from warehouse to office use at ground floor level [c.270sq.m GFA] and refurbishment of the existing first-floor office [c.263sq.m GFA] in the north of the unit. The office space [c.533sq.m Total GFA] will comprise individual offices, meeting rooms, stairwells and circulation areas, storage areas, plant, canteen facilities, and WC facilities - including a new accessible WC on the ground floor. The proposed works will also include the reinstatement of existing windows and an entrance, the opening of blind windows, and the installation of a new window on the west elevation. (ii) Change of use from motor showroom, including ancillary workshop and office / storage areas, to warehousing [c.1,056sq.m + c.1,065sq.m. GFA] in the south of the unit. The proposed works will include the demolition of internal partition walls, floors, stairs, and doorways in the south-east of the unit. The works will also include the removal of a mezzanine level in the south-west of the unit [c.130sq.m.] and the installation of two new free-standing mezzanine levels [1,056sq.m. GFA at first floor level + 1,056sq.m. GFA at second floor level] with associated stairwells and a service lift in the south-west of the unit. (iii) Reconfiguration of the car park layout to the south and west of the unit to accommodate 35 no. car parking spaces, including 2 no. accessible spaces and 7 no. electric vehicle (EV) charging spaces, and a service yard to the north-east of the unit. (iv) Provision of 15 no. bicycle stands under a dedicated shelter located to the north of the unit, providing secure long-term parking for up to 30 no. bicycles, and provision of 2 no. bicycle stands to the west of the unit, providing short-term parking for up to 4 no. bicycles. (v) Repurposing of the external plant room to a bin store. (vi) Reinstatement and rebranding of 2 no. previously permitted pylon signs (Reg. Ref. SD15A/0190), located to the west and south-west of the unit, respectively. (vii) Provision of designated signage zones located above the glazed sections at the south-west corner of the building, as well as above the office and warehouse entrances on the west and south elevations. (viii) Provision of hard and soft landscaping, including the planting of native trees along the southern and western boundaries. (2) Retention permission for the existing pylon sign located at the main entrance to the site in the south-east corner. The pylon sign is to be rebranded. (3) All associated site development and services work on a site of c.0.8609ha.Decision record indexed
    Decision03 October 2025View record
  23. © OpenStreetMap
    WEB2846/25Granted

    9, Seaview Avenue North, Clontarf, Dublin 3

    The development consists of (1) Alterations to the existing house, including relocation of the entrance door and new bay window with flat roof to the front elevation. New windows and doors, roof re-tiled, 7.No velux type rooflights and external insulation to walls. (3) Provision of new single storey extension with flat roofs, 2.No chimneys and 2.No rooflights, along with a covered Veranda to the rear of the existing single storey pitched roof dwelling. (4) A new single storey Studio/Home Office structure with a monopitch roof and 2.No rooflights along the rear laneway boundary, with a new entrance door to the laneway. (5) Alterations to the existing Garage, main door widened, walls externally insulated, roof re-tiled and 1.No Velux type rooflight fitted. (6) New timber fences of various height along the western boundary. (7) Demolitions to include chimney stack, pitched roof extension to rear, and rear boundary wall to laneway, along with all civil, drainage and landscaping works associated with the development.Decision record indexed
    Decision01 October 2025View record
  24. © OpenStreetMap
    2560700Granted

    10 Castlesize Way, Sallins, Co. Kildare

    For alterations during the course of construction to the planning file granted planning permission under file ref; 21/1131, the alterations are, (a) an increase in floor area of 8m2 at first floor level to the rear (North) elevation, this is in addition to the floor area granted planning permission under file ref; 21/1131, (b) a two storey gable roof to the rear (North) elevation, over the increased floor area of 8m2, (c) a change in the main house roof design from hipped roof to a gable roof to side (West) elevation, (c) the installation of side screens to the front door on the front (South) elevation, (d) change in window size at first floor level to front (South) elevation, (e) change in window and double door layout on rear (North) elevation at ground and first floor, (f) a revised internal layout on ground and first floor and (g) all associated works.Decision record indexed
    Decision30 September 2025View record
  25. © OpenStreetMap
    SD25B/0408WGranted

    20B, Airlie Heights, Lucan, Co. Dublin, K78 YP08

    The development seeking permission will consist of the construction of a two-storey extension to the (west) side of the main house, apply brick to the ground-floor front (north) façade and all associated site works. The development seeking retention permission consists of the construction of a first-floor extension to the rear of the house and all associated site works.Decision record indexed
    Decision26 September 2025View record
  26. © OpenStreetMap
    24/5935Granted

    Carrigaline Town Centre Carrigaline West Carrigaline Co Cork

    Permission for the construction of a mixed use development at Carrigaline Town Centre on a 1.84 ha site consisting of 88 no. residential housing units (23 no. 1 beds, 47 no. 2 beds and 18 no. 3 beds). 5 no. ground floor retail units are proposed in the form of a café, gym, hair salon, day care and news agents comprising 886.3 m2. Permission is also sought for the development outlined herein as well as 48 no. car parking spaces and 128 no. bicycle parking spaces. Pedestrian access is proposed to the east off Main Street R611 and to the north of the site off Pottery Road, vehicular access is proposed to the west and will be a continuation of the existing public street. Permission is also sought for all associated drainage, landscaping, bin storage, plant, set down areas, delivery/loading bays etc. and all associated site development and infrastructure works. A Natura Impact Statement will be submitted to the Planning Authority with the application.Decision record indexed
    Decision17 September 2025View record
  27. © OpenStreetMap
    2560483Granted

    Lands at Dundalk North Business Park, Armagh Road, Sportman Hall Co. Louth

    The development will consist of: (1) Construction of a light industrial / manufacturing facility [c.15,967sq.m GFA / height c.14.57m]. The main facility will include manufacturing and warehousing areas at ground floor, with production offices and storage at first floor / mezzanine-levels. Ancillary uses will consist of research and development (R&D) and office space, a reception / showroom, stair and lift cores, circulation areas, and staff welfare amenities, all extending over two floors in the north and west of the facility. (2) A pedestrian and vehicular access and egress point to the west of the facility and a HGV access and egress point to the south-west of the facility, both connecting to the internal road network of the Dundalk North Business Park. (3) Provision of 200 no. car parking spaces, including 10 no. accessible spaces and 40 no. electric vehicle (EV) charging spaces, and 14 no. motorcycle parking spaces, located to the west of the facility. (4) Provision of 40 no. covered bicycle parking spaces, located to the north (10 no. spaces) and west (30 no. spaces) of the facility. (5) A service / marshalling yard to the east and south of the facility. (6) Provision of out / utility buildings [c.1,329.9sq.m. GFA], shelter structures, external storage, battery storage, plant, a generator, a transformer, sprinkler tank and pump house. (7) An ESB substation and switchroom to the north-west of the facility. (8) A R&D yard to the north of the facility, comprising of varying terrains and slopes, a viewing platform, a machine wash area, a machine compound, and a bio-retention SuDS area. (9) Provision of site lighting, security fencing, and gates. (10) Installation of PV panels at roof level. (11) Erection of building mounted signage on the north, east and west elevations [(c.5m high x c.3m wide) x 3 no. signs] and an illuminated totem sign located at the facilities main entrance [c.2m high x c.1m wide]. (12) The erection of a retaining wall, an acoustic fence, and a berm with screen planting along the eastern boundary, and a berm with screen planting to the north and west of the R&D yard. (13) All hard and soft landscaping works, including the provision of SuDS features, surface treatments, planting, and boundary treatments. (14) All associated site development works, including above and below ground services, on a site of c.6.39ha.Decision record indexed
    Decision15 September 2025View record
  28. © OpenStreetMap
    258003Granted

    Beechpark Machinery Yard, Beechpark, Ennis Co Clare

    To carry out the following development: for Beechpark Machinery Yard building & site upgrade, proposed works to include: 1) Construction of a new 162m2 storage shed located at the rear (north) of the site. 2) Reroofing and recladding of the existing warehouse and office building. 3) Provision of 47 no. car parking spaces, 7 no van parking spaces, 7 no. rigid lorry bays and 3 no. articulated lorry parking bays & 2 no. accessible parking bays. 4) Provision 9 no. EV Charging spaces. 5) Removal of existing boundary fencing and entry gate and provision of new palisade boundary fencing with sliding entry gate. 6) Demarcation of new pedestrian crossing area. 7) Installation of solar panels to southwest facing side of main warehouse and office building roof. 8) Provision of rainwater harvesting system and new surface water attenuation area. 9) Provision of service area for mobile library. 10) All ancillary site works and services. In accordance with the habitats Directive, Appropriate Assessment Screening has been carried out on the project, and the screening report accompanies this application. In accordance with Articles 81 and 120 of the Planning & Development Regulations 2001, (as amended), Clare County Council has concluded from an EIA screening determination that no significant effects on the environment are likely as a result of the proposed development and that an Environmental Impact Assessment is not requiredDecision record indexed
    Decision15 September 2025View record
  29. © OpenStreetMap
    25144Refused

    Lough Derg Yacht Club, Dromineer, Nenagh Co. Tipperary

    Improvements to the boat mooring facilities at the western shoreline of the north jetty at the applicant's landholding to include a) removal of existing timber edge decking, localised re-alignment of the shoreline on the south-western section of the north jetty with new c. 2 m wide walkway/pier edge constructed on a line of a new stone filled galvanised steel mesh gabions topped with sustainable hardwood jetty edging and bitmac path onshore, b) proprietary "Versa-Dock" part floating docking system for mooring an RNLI rescue rigid inflatable boat (RIB) to facilitate rapid launching in emergencies and safe mooring of the RIB, c) low bollard type (c. 1.4 m high) safety lighting, d) underground services - electrical supplies, cables, hubs, water supplies from the existing LDYC water services system, e) domestic effluent pump-out station for sailing and motor boats (mainly cruisers) with receiving/pumping station to connect to existing foul effluent sewerage system at the Club, associated drainage and site works, f) landscaping enhancements - selection of indigenous tree species to provide wind protection to the moorings and to provide screening from the lakeGrounds not yet categorised
    Decision11 September 2025View record
  30. © OpenStreetMap
    FW25A/0314EGranted

    Lands at Hansfield, Dublin 15, being part of Zone 1 ‘Main Street North

    The proposed development will consist of minor modifications to the peDecision record indexed
    Decision11 September 2025View record
  31. © OpenStreetMap
    2560436Granted

    Teach Darraigh, Ballycarroll, Stradbally Co. Laois

    Modify the north-east and north-west elevations of the existing dwelling, the change of use of the existing garage to accommodate a living room and gym with the addition of a new A-type roof, a single-storey rear extension linking the main dwelling to the converted garage, and all associated site worksDecision record indexed
    Decision09 September 2025View record
  32. © OpenStreetMap
    2560389Granted

    2 Newcourt Avenue, Bray, Co. Wicklow

    Widened vehicular entrance; dropped cill height to existing window at front; construction of a single storey pitched-roof extension in place of existing conservatory to the south-eastern side of existing house; new pitched dormer window to rear with ridge height to match existing house; extension of existing dormer window to south west, to match dimension of existing dormer window to north-east; new rooflight to north-west slope of main roof; new hard and soft landscaping and all ancillary worksDecision record indexed
    Decision09 September 2025View record
  33. © OpenStreetMap
    2560504Granted

    Mayfield, Claremorris, Co.Mayo

    The development will consist of minor modifications to the previously approved application Ref 24/60137. The extent of these modifications are listed below and highlighted on the drawings enclosed in this application. • Additional stone cladding to South, West and North elevations as indicated on the elevations. • Addition of metal clad canopy to the south façade at main entrance door as indicated on the elevations.Decision record indexed
    Decision08 September 2025View record
  34. © OpenStreetMap
    2560745Granted

    The Lidl site at lands to the west and north of Saint Peter and Saint Paul’s Catholic Church, Main Street, Dunboyne Co. Meath

    Retention permission for development which consisted of: the relocation and construction of the ESB substation building from its permitted location on the northern boundary of the site to the north east boundary of the site. Permission is sought for development that will consist of: (1) amendments to the car parking layout of the development to facilitate 4 Electric Vehicle (EV) parking spaces (serviced by two 50KwHr chargers) and 2 operational spaces for staff; and 20% of other parking spaces ducted for future EV parking. (2) The proposed development includes an updated lighting scheme and underground drainage proposals as well as updated path and curbing details. (3) The proposed amendments are in contravention of condition 12 of ABP Ref: ABP-315651-23. The proposed levels of EV parking and ducting are in accordance with the standards set out in the Meath County Development Plan 2021-2027. (4) All works necessary to carry out and complete the developmentDecision record indexed
    Decision05 September 2025View record
  35. © OpenStreetMap
    25104Granted

    Curtlestown Lower, Enniskerry, Co. Wicklow

    Extend and retrofit existing family home to include a home office, a gymnasium, and a home cinema, with internal courtyards and ancillary accommodation, all located in a below ground basement. Carry out internal alterations to reconfigure the internal spaces of the existing residence. Construct a single storey extension to the kitchen/living and dining area to the south of the residence. Construct a single storey extension to the east of the residence to accommodate a bedroom and ensuite bathroom. Re-position of the main entrance from the north-west elevation to the north-east elevation. Modification of the existing drainage network and upgrade of the waste water treatment system. Carry out some landscaping works to ensure that the below ground level extension and its terrace above is fully integrated into the existing landscape. Permission to retain a single storey cottage associated with the family use of the main residence, located to the north of the existing dwellingDecision record indexed
    Decision03 September 2025View record
  36. © OpenStreetMap
    2560516Refused

    Site located in the townland of Moneybig and Bogland, to the north of Existing Kish Business Park, Arklow

    - 2 no. warehouse buildings with a gross floor area (GFA) of c. 3,364 sq.m each and a total height of c. 14.1m. Each warehouse includes a warehouse area of c. 2,419 sq.m, reception area, office, staff facilities, toilets, plant and storage areas at ground floor level, and office space, meeting rooms, staff facilities, toilets, plant and storage facilities at mezzanine level (c. 581 sq.m). - The provision of a service yard with a security hut (c. 34 sq.m) located at the main entrance, HGV unloading areas and 4 no. associated loading bay docks on the eastern elevation of each warehouse building. - The provision of 68 no. car parking spaces including 4 no. accessible spaces and 10 no. EV parking spaces serving staff and visitors. - The provision of 40 no. cycle parking spaces serving staff and visitors. - The provision of a sprinkler tank, sprinkler pump house (c. 13.3 sq.m), fire hydrant tank, hydrant pump house (c. 13.3 sq.m) and ESB substation (c. 25 sq.m) - Construction of a solar farm development consisting of photovoltaic (PV) panel arrays covering an area of approximately c. 15.7 ha on ground mounted steel frames, associated power trunk building (c. 539 sq.m) and 2 no. transformer compounds, underground cabling and ducting, new internal tracks for maintenance and all associated site services works. - Site access from the permitted development to south (WCC Reg. Ref.: 20/1088 as amended WCC Reg. Ref.: 23/62 and 24/88), which is subject to a current separate amendment application under WCC Reg. Ref.: 25/60350, and extension of the permitted inner relief road through the site. - The provision of a new statcom compound including a single storey control and valve building with a GFA of c. 253 sq.m and associated equipment adjacent to the permitted inner relief road to the south of the main site area. The proposed development also includes for the provision of associated landscaping and planting, berms, boundary treatments, internal road network, pedestrian and cyclist infrastructure, signage zones, site lighting, drainage works, sustainable drainage systems (SuDS) and all ancillary site development worksGrounds not yet categorised
    Decision27 August 2025View record
  37. © OpenStreetMap
    25131Granted

    Ballaghgar, Carrig, Birr

    Demolition of an existing porch to the north west and part of a single storey extension to the south east, removal of an existing chimney and the proposed construction of single storey extensions to both north west and south west with a two-storey extension to the the south east. Proposed additions and adjustments to existing window and door opes on all elevations, works to main roof, all internal modifications. Altering of site boundary and all associated site works.Decision record indexed
    Decision19 August 2025View record
  38. © OpenStreetMap
    FW25A/0275EGranted

    Lands at Hansfield, Dublin 15, being part of Zone 1 ‘Main Street North

    The site is located on lands to the east side of Station Road, HansfieDecision record indexed
    Decision19 August 2025View record
  39. © OpenStreetMap
    SD25A/0145WGranted

    Lands at Main Street, Newcastle, Co. Dublin

    Change of use of the permitted pharmacy unit (approx. 251sq.m net) as granted under parent planning ref. S020A/0037 and previous change of use planning ref. SD21A/0311 to use as part Pharmacy (approx. 75 sq.m net) and part Medical Centre (approx. 176 sq.m.) with all associated internal and external layout alterations to facilitate this change of use; internal layout changes at ground floor include the partitioning of both units, external layout changes include the provision of an additional window on the south elevation and additional signage on north, south east and west elevations totalling 13 sq.m. with proposed opening hours 7am-7pm 7 days a week.Decision record indexed
    Decision11 August 2025View record
  40. © OpenStreetMap
    25203Granted

    5 The Terrace, Mountcollins, Co. Limerick.

    A) flat roof extension to rear de bungalow (north side) with all associated site works. (b) retention of flat roof extension to rear of bungalow (south side) with all associated site works. c) Planning Permission to replace flat roof on extension to rear of bungalow (south side) with pitched tile roof to match main house with all associated site worksDecision record indexed
    Decision08 August 2025View record
  41. © OpenStreetMap
    3254/25Granted

    393 Clontarf Road, Clontarf East, Dublin 3, D03 Y599

    (A) The removal of existing single storey extension to the rear.(B) The construction of a new single storey extension to the rear with flat sedum roof and two roof lights.(C) The conversion of existing attic to habitable floor area. ((D) The construction of three new dormers, one flat roof dormer with metal cladding to the rear (North West Elevation) and two pitched roof dormers with select roof tile finish to the front (South East Elevation). (E) The addition of one single rooflight to the main pitched roof to the rear (North West Elevation) (F) Internal configuration of existing layout (G) All ancillary site and landscaping works.Decision record indexed
    Decision07 August 2025View record
  42. © OpenStreetMap
    WEB2689/24Granted

    Rotunda Hospital Campus, Parnell Square, Dublin 1

    PROTECTED STRUCTURE The proposed development comprises a 4-storey over basement maternity hospital building extension (Critical Care Wing, c. 9,946 sq m gross floor area) including: 80no. additional hospital bedrooms, new theatre and ancillary facilities, a new link corridor (Level 02) and connections with the existing Entrance Building and Main Hospital Building (protected structure); and, all ancillary demolition, site development, conservation, and landscaping and boundary works on campus, including: -•Associated refurbishment works within the existing Entrance Building. •Refurbishment of the existing ward space on Level 02 within the Plunkett Cairns Wing, Medical Residence Building and Main Hospital Building (Protected Structures). •Plant at basement of the proposed new Critical Care Wing. •Chimney flues, plant and associated screening at roof level of the proposed new Critical Care Wing and at roof level of the existing Entrance Building. •Demolition of - existing single-storey Outpatient department (c.1,174 sq m GFA), vehicular ramps and tunnel; - existing plant structures, including single-storey plant/waste store, low voltage switch room and defunct water tank, in the central garden area. •Construction of a new single-storey bicycle store to provide an additional 98no. bicycle spaces at surface level. •Replacement of the existing vehicular access ramps with two new realigned vehicular access ramps to the existing lower-level surface car parks. •Reconfiguration of the existing lower-level surface car parks, including removal of 67no. existing car parking spaces. •Relocation of the existing waste compactors, from north of the original hospital building (protected structure), to new location in the reconfigured lower-level surface car park area with associated landscape screening. •Relocation of the existing medical waste store to an external storage area, under the proposed new access ramp with associated removal of an existing caged clinical waste store. •Construction of a screened generator and medical gases compound within the northern portion of the site. •Hard & soft landscaping elements to the perimeter of the proposed building and carparks including the creation of a lightwell behind the existing boundary railings. •Minor reconfiguration, removal (c.10m) and making good of the protected boundary railings along the western perimeter of the site.•Replacement of the existing pedestrian and vehicular entrance gates at the northwest perimeter of the site.Decision record indexed
    Decision31 July 2025View record
  43. © OpenStreetMap
    2460295Refused

    Rathrush Emlicon and Bendinstown, Ballon, Co. Carlow

    For a ten-year planning permission for a renewable energy development comprising the construction of a c. 63MW solar farm of 118.9ha and associated works in the Townlands of Rathrush, Emlicon and Bendinstown, Co Carlow. The proposed development will consist of: • A c. 63MW solar farm comprising ground mounted solar photovoltaic panels. • 15 No. Invertor Combiner Kiosk /Transformers and hardstands. • 1 No. Ring Main Unit. • 2 No. spare parts storage containers. • Provision of site access tracks and upgrading of existing tracks. • Underground cabling within the solar farm site, in private lands and under the L7111, L7114, L7115 local roads to connect the solar farm field parcels, and to connect the solar farm to the permitted Garreenleen Substation. • 3 No. temporary construction compounds. • Demolition of derelict agricultural building and disused silage storage structure. • Upgrading and widening works at Site entrances. • All ancillary development including such as an up to 2.4m high stock proof fence, CCTV and drainage infrastructure. This application is seeking a ten-year permission and a 35-year operational period from the date of overall commissioning of the solar farm. This application is accompanied by a Natura Impact Statement (NIS)
    Traffic Sightlines
    Decision31 July 2025View record
  44. © OpenStreetMap
    WEBDSDZ2279/25Granted

    The Shipping Office, 20-26, Sir John Rogerson's Quay, Dublin 2, D02 Y049

    PROTECTED STRUCTURE: The application relates to a proposed development within the North Lotts and Grand Canal Dock Strategic Development Zone Planning Scheme area. Planning Permission is sought for erection of new tenant identification signage/branding, on the setback wall adjacent to the main entrance of completed office building 'The Shipping Office' (completed under DCC Grant reg. ref. DSDZ4006/19); At THE SHIPPING OFFICE, 20-26 SIR JOHN ROGERSON'S QUAY, DUBLIN 2, D02 Y049 (20-24 Sir John Rogerson's Quay is a Protected Structure RPS. No. 7547) by Balark Trading GP Limited.Decision record indexed
    Decision29 July 2025View record
  45. © OpenStreetMap
    WEB1158/25Granted

    65, Shelmartin Avenue, Dublin 3, D03 P9C0

    The construction of a new extension and new bay window to the rear of main house, a new porch to the front and side of main house, a first floor window on north gable, external insulation on existing house, new north boundary at front and all associated ancillary works including demolition as necessary to facilitate new construction.Decision record indexed
    Decision25 July 2025View record
  46. © OpenStreetMap
    25/5034Granted

    Inchera Little Island Co.Cork

    Permission for the proposed development will consist of the completion of the Renewable Biogas Plant as permitted by extant planning permission ref. 15/4926, extended by ref 20/5549 and amended by ref 23/5586. All demolition, site clearance, earthworks and formation for foundations will be complete under the current permission. The proposed plant will generate renewable biogas from 90,000 tonnes of non-hazardous biodegradable waste (‘Brown bin’ domestic and commercial waste) per annum utilising anaerobic digestion (AD) technology. It is proposed to upgrade the biogas to biomethane and inject it into the adjacent gas grid to replace fossil fuel derived natural gas. Other products from the process include digestate (a nutrient rich biofertilizer) as well as biogenic (natural) carbon dioxide. The proposed development will consist of the construction of: 1) main process building (c.3,762m2 gross floor area (GFA), max 14.5m high) incorporating feedstock reception and processing area, digestate treatment areas, dewatering and storage areas, quarantine areas, an odour control system and associated 25m high stack with signage on the south elevation. 2)Tank farm (c. 3,183m3 footprint, 4m high bund wall) encompassing a total of 6 tanks including four digestor tanks (20.15m max. height, c.3,400m3 capacity) a digestate storage tank (20.15m max. height, c.3,400m3 capacity), a suspension buffer tank ( 10.5m max.height, c.700m3 capacity (, an containerised desulphurisation plant and associated 2 tanks (14m max height, c120m3 capacity), 2 no. enclosed pump rooms (room no.1 -53.58m2 GFA and room no.2 – 23.69m2 GFA), and enclosed feedstock pump room (53.58m2 GFA and 3.6m high), 3 sediment settlement tanks (c.5.84(L), c.2.23m (W) & c.3.78(H) on a raised platform at 6m above ground level, stairwells, pumps, gantry walkways, 2 bund access stairs and tank emergency access ladders; 3) A biogas upgrade plant and gas entry unit; 1 no. containerised Combined Heat and Power (CHP) 1.5MW unit with an associated 28m high stack, a carbon dioxide liquefaction plant, a biogas holder (10.56 max. height, c.2,000m3) with 4 no. c.13.12m high lightning rods, a 9.26m gas flare, a containerised boiler with 10m stack, a transformer station, a propane storage tank, an emergency generator, 2 no. weighbridges, weighbridge office (c.17.2m2 GFA and 4.55m high), a fire water tank (c.1,000m3 and 14.12m high), a bunded vehicle refuelling area with a fuel storage tank (2.5m3) and a wheel wash, 4) Administration building (c.393.25m2 GFA) and a workshop (c.70m2 GFA), 5) 31 car parking spaces (including 2 electric vehicle charging points and a universal parking space), 2 motorcycle parking spaces and a covered bicycle rack; 6) Boundary treatment including 2.4m high perimeter fencing (mix of mesh wire fencing and acoustic fencing), access gates on the south western and north eastern boundaries; and 7) all ancillary site development works and services including landscaping, lighting, 2 no. directional signs, service yard area and internal circulation routes, pipe bridge, footpath and all site drainage works. The application relates to development which comprises or is for the purpose of an activity requiring an Industrial Emissions Directive Licence issued by the Environmental Protection Agency, reg. no. P1018-01. An Environmental Impact Assessment Report (EIAR) and a Natura Impact Statement (NIS) have been prepared and will be submitted to the planning authority with the application.Decision record indexed
    Decision24 July 2025View record
  47. © OpenStreetMap
    25/4506Granted

    The IDA Business & Technology Park Tullagreen and Anngrove (townlands) Carrigtwohill Co. Cork

    Alterations to the extension and expansion of their existing facility permitted by Cork County Council planning references 23/5968 and 23/6412 and all ancillary site development works. The proposed development includes alterations to planning reference 23/5968 comprising the omission of a permitted detention basin and replacement with Stormcell attenuation system. The proposed development also includes alterations to planning reference 23/6412 comprising: (i) The construction of a revised extension to the existing GE Healthcare building comprising a filling line, solution preparation and utilities building with an approximate maximum height of 13 metres (reduction from approximate maximum height of 27 metres). (ii) The reduction in area and reconfiguration of the permitted utilities yard/contractors compound to include a utilities building, electrical building, pump house, waste compactor building, nitrogen tank, mains water tank, piperacks to the proposed new filling line and solution preparation building and all ancillary plant and service infrastructure. The works provide for the maintenance of the existing project cabin and workshop buildings on site, with partial demolition of the workshop building. (iii) The relocation west of the existing vehicular site entrance from the north and associated realignment of the internal service road within the site. (iv) All other ancillary site development and enabling works which include rooftop PV panels, signage, revised servicing and drainage proposals, landscaping works and establishment of a temporary construction compound (area to be reinstated post construction phase) A Natura Impact Statement (NIS) has been prepared and will be submitted to the Planning Authority with the application.Decision record indexed
    Decision21 July 2025View record
  48. © OpenStreetMap
    WEB2172/25Granted

    88, Kimmage Road West, Dublin 12

    The proposed development will comprise the following: Demolition of the existing single-storey rear extension; Elevations amendments to existing front porch as main entrance; Construction of a new part single-storey, part two-storey rear extension; Internal reconfiguration to convert the existing 3-bedroom semi-detached dwelling into a 4 bedroom dwelling; Removal of the existing chimney on the north elevation; Installation of 1 no skylight on the new two-storey extension facing East; Addition of a single door to the front porch; Proposed side extension over existing garage. All works to be carried out with associated site development works.Decision record indexed
    Decision21 July 2025View record
  49. © OpenStreetMap
    2560488Granted

    0.1 hectare site at Springfield Centre, Old Singland Road, Limerick

    The change of use of the 958.5 sq.m gross floorspace vacant two storey over basement building from pub/restaurant use a community resource hub to be operated by MS Ireland. The proposal will comprise of: At basement - 3 no. meeting rooms with ancillary office; Staff canteen; Staff changing area; Ancillary areas – circulation, WC, showers, storage, etc. At ground floor: Flexible studio; Gym; Reception / lounge area with kitchenette; Meeting room; Admin office; 1 no. treatment room with office; Ancillary areas – circulation, WC, showers, storage, etc. At first floor: Open plan office; Ancillary areas – circulation, WC, showers, storage, etc. Externally: Soft landscaping to north; Bicycle shelter with sheltered and secure parking for 10 no. bicycles; Refuse storage area with capacity for 3 no. 1,100 litre bins, to allow for recycling and waste segregation; 1 no. MS Ireland signage at first floor level, backlit, to north elevation; 1 no. MS Ireland signage at first floor level, backlit, to east elevation; 1 no. backlit signage panel adjacent to main entrance door at ground floor level; replacement of existing timber cladding with timber effect composite or similar. The proposed development includes all associated and ancillary works, including internal fit-out works and new AOVs to roof.Decision record indexed
    Decision18 July 2025View record
  50. © OpenStreetMap
    2460817Granted

    IDA Drogheda North Business Park, Mell and Moneymore, Drogheda Co. Louth

    Permission for the provision of a new wastewater pumping station, rising main and all associated and ancillary development works, including new hardstand areas, kiosks, vent columns, light poles, underground tanks and chambers, landscape reinstatement works, connections to electricity supply network and water supply network and site drainageDecision record indexed
    Decision11 July 2025View record
Showing 51-100 of 830