  1. © OpenStreetMap
    24/4026Granted

    0.56 hectares site within ESB Aghada Generating Station Ballincarroonig Aghada Co Cork P25 XE94

    The proposed development consists of the construction of a hydrogen production facility comprising a hydrogen compound and contractor’s compound with all associated site access and ancillary site development works. The proposed development will demonstrate the full chain hydrogen production via electrolysis, storage, usage on site via fuel cell and transport offsite to other sector hydrogen users. The proposed development is to be used for hydrogen production for an operational period of up to five years. The proposed development comprises: 1) 1 megawatt (MW) electrolyser including a water purification unit (40-foot (ft) container) (2.5m x 12.2m x 5.4m) with a stack height of 7.7m above ground level, 2) A transformer and control unit container (2.8m x 7.5m x 3.3m) housing a 6.6 kilovolt (kV) to 400kV transformer, 3) A storage container (2.8m x 6.4m x 3.3m), 4) A welfare unit (2.8m x 7.5m x 3.3m), 5) A compressor (20ft container) (2.7m x 6.4m x 4.3m), 6) 5 x 2.5kg low pressure (30 bar) hydrogen storage MCP units (manifolded cylinder pallets) (1m x 1m x 2.1m), 7) 3 x 19kg high pressure (300 bar) hydrogen storage MCP units (manifolded cylinder pallets) (1m x 1m x 2.1m), 8) 2 x 61kg low pressure (30 bar) nitrogen storage MCP units (manifolded cylinder pallets) (1m x 1m x 2.1m), 9) 2 x 31kg high pressure (300 bar) nitrogen storage MCP units (manifolded cylinder pallets) (1m x 1m x 2.1m), 10) 4 x 400kg (high pressure) mobile refuelling hydrogen storage vehicles, 11) 2 x 250 kilowatt (kW) hydrogen power units (2.7m x 7.3m x 5.4m), 12) Heavy goods vehicles (HGV) loading bays with 4m high walls, 13) A palisade fence enclosing the hydrogen compound (2.6m height). In addition to the above, planning permission is also sought for all ancillary site and development works to facilitate the development including the MCP filling area, internal site access road, 3 no. car parking spaces, 2 no. EV chargers, barrier, lighting and CCTV, drainage infrastructure and pipe racks/cable trays. After up to five years in operation, the decommissioning phase of the proposed development will comprise the removal of the electrolyser, transformer and control unit container, compressor, MCP units, mobile refuelling hydrogen storage vehicles, hydrogen power units, storage container and welfare unit from the site and removal of loading bay walls to level in line with the concrete yard. The contractors compound area will be reinstated to its present condition during decommissioning. It is proposed that all utility service connections and all other structures and installations on site including, but not limited to, the hydrogen compound fencing, concrete yard, lighting and CCTV will be retained on site in perpetuity. The proposed development consists of an activity for which an Industrial Emissions Licence is required. ESB Aghada Generating Station is a registered lower tier establishment under the Control of Major Accident Hazard (COMAH) Regulations, 2015. The development will consist of the provision of, or modifications to, an establishment within the meaning of Part 11 of the Planning and Development Regulations (Major Accidents Directive). A Natura Impact Statement (NIS) will be submitted to the planning authority with the application.Decision record indexed
    Decision05 March 2024View record
  2. © OpenStreetMap
    23/5104Granted

    ESB Aghada Generating Station Ballincarroonig Aghada Co Cork

    Development is sought for a period of 10 years at a 10.22 hectares site within ESB Aghada Generating Station consisting of 1) Construction/installation of an open cycle gas turbine (OCGT) generating unit and associated plant and equipment, comprising the following main components with approximate dimensions as stated: Gas turbine air intake [24m x 18m x 26m high], Generator enclosure [24m x 18m x 14.5m high], Gas turbine enclosure [53m x 15m x 26m high], Exhauster diffuser [14.5m x 10.4m x 10.5m high], Exhaust stack [40m high, 8m diameter], Gas turbine control and electrical modules [20.5m x 18m x 10m high], Fin fan coolers [27m x 19m x 8m high], Main transformer [12.2m x 7.5m x 8.5m high] including 17.6m x 17.9m concrete bund; and 2 no. 12m high concrete blast walls, Auxiliary transformer [5m x 4.7m x 7.5m high] including 6.8m x 7.5m concrete bund; and 2 no. 12m high concrete blast walls, Demineralised water treatment plant [20m x 10m x 5.4m high], Demin water storage tank [14.63m high x 24.4m diameter], Raw water/Firewater storage tank [14.63m high x 15.2m diameter], Fuel oil storage tanks [two, each 12.19m high x 17.4, diameter], including 67m x 35m concrete bund, Fuel oil forwarding pumps [6m x 10m x 2.2m high], Firefighting pumphouse [10m x 7m x 5.4m high], Gas conditioning compound [42.3m x 11.5m x 6m high]. Above ground installation gas compound expansion [23m x 73m], Indoor switchgear building [20m x 30m x 18m high], Emergency diesel generator <1 MW [10m x 4m x 5m high], Generator circuit breaker [8.8m x 5.1m x 4m high], Continuous emissions monitoring skid [3.5 m x 2.5m x 5m high], Workshop/Stores/Administration building [35.9m x 12m x 15m], Hydrogen storage compound [8m x 4m x 2m high], Surface water drainage system, Vehicle parking, Internal roadways, 2) Demolition of an existing single storey stores building, 3) connection to the existing on-site above ground installation (AGI), 4) Connection to the National Grid by means of underground cable to existing on-site 220kV substation, 5) All associated works to facilitate the development such as temporary construction compounds, perimeter fencing, use of an existing access to public road, above ground pipe racks, underground cables on the site and crossing the R630 roadway, site lighting and telecommunications. The development consists of an activity for which an Industrial Emissions Licence is required. ESB Aghada Generating Station is a registered lower tier establishment under the Control of MaDecision record indexed
    Decision02 November 2023View record
  3. © OpenStreetMap
    20/6463Granted

    Townlands of Knockanemorney TD, Ballynafarsid TD, Aghada TD, Curragh, Mosestown TD, Ballincarroonig Corkbeg, TD, Ardnabourkey TD, Glanagow TD, Trabolgan, Ballytigeen, Co. Cork

    The development which consists of the construction of a sewerage scheme, landscaping and associated site works, for the villages of Whitegate and Aghada. The scheme consists of the following components: A) A proposed wastewater treatment plant (WWTP) at Ballytigeen TD, with associated and ancillary development works including an access road, tanks, storage facilities, inlet works, all associated site development works, boundary fencing around the perimeter of the WWTP, a gravity sewer and long sea outfall to convey treated discharge effluent from the WWTP to White Bay through Glanagow TD and Trabolgan TD. B) A proposed underground wastewater pump station and associated infrastructure in Rostellan at the Thomas Kent Memorial Park at Knockanemorney TD, including an underground pump sump, underground stormwater storage tank, valve and flowmeter chambers, manholes, pipework, access road and gate, control kiosks and vent stack. C) A proposed rising main at Knockanemorney TD, Ballynafarsid TD and Aghada TD, to convey flows from the proposed Rostellan pump station to a proposed pump station in Lower Aghada. D) A proposed underground wastewater pump station and associated infrastructure at Lower Aghada located west of the pier at Aghada TD, including an underground pump sump, underground stormwater storage tank, valve and flowmeter chambers, manholes, pipework, access road, gate, control kiosks, a surge vessel, a vent stack and the decommissioning of an existing package wastewater treatment plant. E) A proposed rising main to convey flows from the proposed Lower Aghada pump station to an existing sewer in the Upper Aghada sewerage network at Aghada TD. F) A proposed upgrade to the existing sewerage system by the replacement of an existing 150mm diameter sewer with a proposed 225mm diameter sewer at Aghada TD and Curragh TD. G) A proposed underground wastewater pump station and associated infrastructure at the Square in Whitegate Village including an underground pump sump, underground stormwater storage tank, valve and flowmeter chambers, manholes, pipework, control kiosks and vent stack, and decommissioning of existing pump station, in Mosestown TD and Ballincarroonig TD. H) A proposed rising main to convey flows from the proposed Whitegate pump station to the proposed WWTP at Mosestown TD, Corkbeg TD, Ardnabourkey TD and Ballytigeen TD. I) A proposed 225mm diameter gravity sewer in Ardnabourkey TD and decommissioning of an existing septic tank. A natura Impact StDecision record indexed
    Decision30 August 2021View record
  4. © OpenStreetMap
    20/4294Granted

    Lands to the east of the R630 in the townlands of Ballincarroonig and Aghada located inside the Aghada Generating Station, Ballincarroonig Whitegate, Co. Cork

    Development on a a c. 1.8 ha site, on ESB lands. The development will consist of a c.19 MW capacity battery storage facility located within a secured compound, and will - subject to detailed design, commercial and technical considerations, include: (a) a control building (c. 112 sq. m., c. 4.7 m high); (b) plant and equipment comprising: (1) up to 12 no. battery container units (c. 30 sq. m. and up to c. 4.7 m high) with roof mounted HVACs; (2) up to 6 no. battery unit transformers on concrete plinths (c. 11 sq. m. and c. 4 m high); (3) up to 6 no. inverter units (c. 30 sq. m. and c. 3 m high); (4) a bunded house transformer (c. 20 sq. m. and c. 3.3 m high) with firewall on three sides; (5) an MV stepdown transformer (c. 60 sq. m. and c. 4.5 m high) with firewall on three sides; (6) VAR supports system on a concrete plinth (c.24 sq. m. and c. 3.4 m high); (7) cable trays and associated service connections; (8) up to 4 no. lightning masts (c. 20 m high); (9) a c. 18 m high SCADA pole; (10) a pole mounted security camera (c. 8.3 m high); (c) c. 2.6 m high palisade fencing and gates; (d) demolition of an existing building (c. 147 sq. m. and c.5.5 m high) and (e) ancillary site clearance and development works including provision of areas of hardstanding, internal access roads, and connections to site services networks. The planning permission is being sought for a 10 year duration. A Natura Impact Statement will be submitted to the Planning Authority with the application. Licensed by the Environment Protection Agency under an Industrial Emissions (IE) License [Ref. P0561-05] and a Lower Tier COMAH site and therefore falls under the requirements of the Control of Major Accident Hazard (COMAH) Regulations, 2015.Decision record indexed
    Decision09 April 2020View record