On the public footpath on the Southern side of the N32, on the West side of the entrance to Saint Michael's House, Belcamp, Dublin 17
RETENTION: The retention of the existing scrolling internally illuminated double sided ‘Metropole’ advertising display case mounted on an offset leg.Decision record indexed
The site of c. 0.94 ha at lands South of Belcamp 220 kV Substation, Belcamp, Dublin 17
Mayne Stability Limited intends to apply for permission for a period of 10 years for the development of access to the Synchronous Compensator Development (Grid Stabililisation Facility) on the site of a c 0.94 ha. at lands south of Belcamp 220KV substation, Belcamp Dublin 17. The proposed development will consist of the following elements within the administrative boundary of Dublin City Council: a) New access entrance from the R139 and a clear span bridge crossing over River Mayne. b) Internal access tracks, security fencing, temporary construction compound, landscaping, and drainage. A concurrent planning application is being made to Fingal County Council which relates to the lands directly to the north of the site of c.1.65 ha for the construction of A Grid Stabilisation Facility containing 1 No. High Inertia Synchronous Compensator (HISC) unit enclosed within a steel clad framed style structure (12.1m max height) and supported by 8 No. electrical equipment containers (containing ancillary power supply products including a static frequency converts, MV switchgear, exciters, LV distribution, control room, welfare and office), main, auxiliary & start-up electrical transformers, generator circuit breaker, switchgear equipment, External cooler units and 1 No. back up diesel generator and associated diesel storage tank; A 220kV High Voltage Gas Insulated Switchgear (GIS) compound containing a GIS building with all control & HV equipment within a single storey building (13.2m max height). The building will be surrounded by a compound road and contained within a 2.6m high galvanised steel palisade fence; A 220kV underground cable to the existing adjoining Eirgrid substation boundary; Associated elements comprising a clear span bridge over the River Mayne, various underground cables and ducts, equipment plinths, boundary security fence, compound lighting and palisade gates and fencing, security lighting, CCTV, internal access roads, hardstanding areas and all necessary foundations works for the above compounds. A Natura Impact Statement (NIS) will be submitted to the Planning Authority with the application. The NIS may be inspected, or purchased at a fee not exceeding the reasonable cost of making a copy, at the offices of the Planning Authority during its public opening hours.Decision record indexed
32, Swift's Grove, Clonshaugh, Dublin 17, D17 AW26
RETENTION: Retain front living room porch single storey extension and front façade first floor level window opening size altered to dwelling house.Decision record indexed
Permission is sought to construct a single storey side extension, alterations to boundary wall with creation of side access and all associated site works.Decision record indexed
The development consists of the construction of a new attic conversion to create storage space with new flat roof dormer to the rear elevation at roof level. The development is to include internal alterations, and all ancillary site works and drainage as required.Decision record indexed
Unit 9, Willsborough Cluster, Clonshaugh Industrial Estate, Dublin 17
The development will consist of installation of external security roller shutters above windows and exit door to west elevation of existing building.Decision record indexed
RETENTION: Retention of alterations to a ground floor extension, permitted by a Grant of Planning Permission 2903/17 dated 5th July 2017. The alterations being the omission of a projecting structure in front of the building line of 3 sq.m area and the provision of a tiled canopy across the full width of the front elevation.Decision record indexed
The development will consist of the creation of new vehicular entrance, construction of additional staff car parking, yard extension and all associated site works.Decision record indexed
The development will consist of a proposed new ground floor only detached building to the side/front of the existing house to be used as a gym/office & storage and all ancillary works.Grounds not yet categorised
The development will consist of the construction of a single storey flat roof side extension to the existing dwelling and with a single storey projection forward of the existing dwelling’s building line with a mono pitch roof over and all necessary ancillary site development works to facilitate this development.Decision record indexed
Planning permission for a single storey pitched roof structure in the rear garden (circa 50 sqm) for use as a utility room, games room/gym and part garden shed with associated site works.Decision record indexed
SPEEDPAK, Units 5-8, Clonshaugh Business & Technology Park, Coolock, Dublin 17
The development will consist of a permanent detached portacabin sized 54 square meters and 3.20 meters high, completed with paving and security fence, located to the east of the existing building.Decision record indexed
Planning permission for development at this site will consist of demolishing an existing shed to the rear of the existing site and building a new ground & first floor extension to the rear of the existing house. A proposed new ground floor only porch to the front of the existing house and all ancillary works.Decision record indexed
RETENTION: permission for 9 no. single storey garden structures located at the rear of Priorswood House, 100, Clonshaugh Avenue, Dublin 17. The structures include (a) 2 no. polly-tunnels for plant propagation and training use (b) 3 no. garden shed for tool storage (c) a plant propagation shed (d) a garden structure for training and compiling horticultural records (e) a structure for woodwork training and storage (f) a structure for trainees rest room and canteen.Decision record indexed
The development will consist of the build of a detached granny flat built at rear of house with bedroom, bathroom and kitchenette.Grounds not yet categorised
The former Diamond Innovations site (Unit 1C), Clonshaugh Business & Technology Park, and adjacent lands, Dublin 17
The development will consist of: A c. 200m long medium/low voltage (MV/LV) underground cable (UGC), to be installed in underground cable ducting in a c. 1m wide trench of depth c. 1m within an area of c.200sq.m., connecting the existing ESB network within the former Diamond Innovations site to the existing ESB Darndale substation. The UGC also includes ancillary electrical equipment. The development includes all associated and ancillary works. An Environmental Impact Assessment Report (EIAR) which complies with the European Union (Planning and Development) (Environmental Impact Assessment) Regulations 2018 (S.I> 296 of 2018) will be submitted to the Planning Authority with the application. The EIAR will be available for inspection or purchase at a fee not exceeding the reasonable cost of making a copy, during office hours at the offices of the planning authority.Decision record indexed
Works to include the retention of a shed to the rear garden of the property that is approximately 3 meters in height from ground to roof level and has a floor area of approximately 42.2 SQM, the said building is proposed to be converted internally to accommodate a music studio, office and secure lock up.Decision record indexed
Planning Permission to install 140kW (750m2) of roof mounted solar PV panels and all associated works on our warehouse at Clonshaugh Industrial Estate, Coolock, Dublin 17.Decision record indexed
Costcutter Supermarket, Unit 4, Pinewood Shopping Centre, Clonshaugh Avenue, Dublin 17
RETENTION PERMISSION sought for two steel container stores at rear of Costcutter Supermarket, Unit 4, Pinewood Shopping Centre, Clonshaugh Avenue, Dublin 17.Decision record indexed
Extension to the side of existing manufacturing facility to consist of single storey warehouse building (Block E) 627 sq.m gross area & all associated site works.Decision record indexed
Woodlands & Former Diamond Innovations Site, Clonshaugh Business & Technology Park, Dublin 17
The development will consist of amendments to approved plans permitted under P.A Reg. Ref:3803/20, to include minor repositioning of transformers, circa 7.8 sq.m of additional bund area per transformer, increase in height of fire walls from 5.5m to 6.5m, overground & underground cable connection to adjacent sub-station permitted under P.A Reg.Ref:3288/16 and 3874/15, associated cable support structures to max height of 4.3m, minor amendments to section of compound fencing and associated siteworks.Decision record indexed
Development will consist of a proposed new 7.5m wide dormer roof to the side of the existing house roof looking out onto Clonshaugh Green and all ancillary works.Decision record indexed
Planning permission for the development will consist of a proposed new ground floor only extension to the rear of the existing house and all ancillary works.Decision record indexed
The development will consist of demolishing existing shed to the side of the existing house and replacing with a new single storey extension to the side and extending down into the rear of the existing house. A new window in the side elevation at attic level. A new flat roof dormer to the rear of the existing house roof and all ancillary works.Decision record indexed
RETENTION Permission. The application consists of an attic conversion for storage purposes only (non-habitable status) with a flat roof dormer window to rear of house, internal alterations & all associated site works.Decision record indexed
Permission for conversion of existing attic space comprising of modification of existing roof structure, roof window to the front, new access stairs and flat roof dormer to the rear.Decision record indexed
The development will consist of demolishing an existing shed to the rear of the existing site and building a new ground & first floor extension to the rear of the existing house. A proposed new ground floor only porch to the front of the existing house and a new window in the side elevation and all ancillary works.Decision record indexed
The development will consist of converting the existing non-habitable roof space to a bedroom by raising the existing ridge height of the roof and building a tiled roof dormer window to the front of the dwelling. The work encompasses all associated internal and site works.Decision record indexed